Day 200 • Nov 16, 2025
Reset
POD Solar — 200MW Demo
West Texas
200 MW
POD Construction Services
Sun, Nov 16, 2025
Day 200 of 280
290
workers on site
13 mph
wind — Crane: GO
199
days safe
Data Sources
— 7 files, 18,832 fields extracted
You have these files
Blocks Complete
18 / 24
MW Energized
149.9 MW
Day
200 / 280
Substation
79%
Bare Ground
(24/24)
Piles Driven
(22/24)
Trackers
(21/24)
Modules
(21/24)
Strung
(20/24)
Combiner
(19/24)
AC Connected
(18/24)
Commissioned
(18/24)
GATE
NORTH FIELD
SOUTH FIELD
34.5 kV
INV-1
INV-2
INV-3
INV-4
138 kV SUBSTATION
79% Complete
TO GRID
LAYDOWN YARD
O&M
POD SOLAR — 200 MW
N
0.5 mi
Plan of Day
Solar Plant Specialty Report
Day 200 • Nov 16, 2025