Day 280 • Jan 5, 2026
Reset
POD Wind — 224MW Demo
Western Kansas
224 MW
POD Construction Services
Mon, Jan 5, 2026
Day 280 of 270
413
workers on site
11 mph
wind — Crane: GO
275
days safe
Data Sources
— 6 files, 16,934 fields extracted
You have these files
Turbines Complete
80 / 80
MW Energized
224 MW
Day
280 / 270
Substation
98%
Survey / Staked
(80/80)
Excavation
(80/80)
Foundation
(80/80)
Tower Base
(80/80)
Tower Mid
(80/80)
Tower Top
(80/80)
Nacelle Set
(80/80)
Hub + Blades
(80/80)
Cable Connected
(80/80)
Commissioned
(80/80)
Cable Routes
POD WIND — 224 MW
GATE
345 kV SUBSTATION
98% Complete
TO GRID (345 kV)
O&M
Operations
LAYDOWN YARD
MET 1
MET 2
WEST FIELD
EAST FIELD
N
1 mi
Plan of Day
Wind Plant Specialty Report
Day 280 • Jan 5, 2026