Plan of Day
Daily Reporting Intelligence
POD-2026-0268
Feb 23, 2026
Daily Project Report
Highway 101 Expansion — Phase 2
At Risk
62°FPartly Cloudy
8 mph
45%
Earned Value Performance
Earned Value Performance
Cost Performance
Critical
0.49CPI × SPI
Schedule Performance
Critical
Both cost and schedule under pressure
CPI
0.70
SPI
0.70
Cost Var-30.0%
Sched Var-30.0%
Composite0.490
EAC Factor1.429
BudgetOver Budget
ScheduleBehind
HealthAction Needed
Budget Summary
Budget Performance
0.00CPI
Current Budget
$0+$0
Spent vs Earned$0of$50.0M
Spent 0%
Earned 0%
Cost Variance+$0
Spend Efficiency0%earning more than spending
Contingency Reserve0%
Budget Remaining$0
Cost Breakdown
$0of $48.5M0% utilized
Labor0%
$0$0
Materials0%
$0$0
Equipment0%
$0$0
Subcontracts0%
$0$0
Overhead0%
$0$0
Budget baseline shown as ghost bar
$0 / $48.5MCash Flow
Cash Flow Analysis
Ratio: 0.00x
Positive
Total Inflow
$0$0 avg/periodTotal Outflow
$0$0 avg/periodNet Position
+$0+$127K avg/periodBest: M12 (+$192K)
Weakest: M1 (+$65K)
Avg Net: +$127K/period
Inflow Outflow Cumulative Net
Margin & Retainage
Profit Margins
Target: 8%
At Risk
0.0%▼ 0.0%
0.0%▼ 0.0%
Gross Margin
0.0%▼ 0.3% vs priorNet Margin
0.0%▼ 3.3% vs priorTarget
8%Net is below target by 11.3%Margin Gap (Overhead Spread)0.0% absorbed by overhead
Gross (-0.3%) Net (-3.3%) Overhead (0% of gross)
Retainage Status
Total Retained$0
Released$0
Still Held$0
Release Progress0% released
Released
Held
Expected Next Release$0
Max retainage on $48.5M contract: $4.8M
Plan of Day
Day 268 • Feb 23, 2026Daily_Report_July15_v3_FINAL_FINAL(2).xlsx
FileHomeInsertPage LayoutFormulasDataReview
B17fx=B15/B16
| A | B | C | D | E | F | G | H | I | J | |
| 1 | Daily Report - Highway 101 | Date: | 7/15/2025 | |||||||
| 2 | ||||||||||
| 3 | SAFETY | |||||||||
| 4 | Incidents: | 0 | Near Misses: | NOT TRACKED | ||||||
| 5 | EMR: | ??? | TRIR: | see email | ||||||
| 6 | ||||||||||
| 7 | SCHEDULE | |||||||||
| 8 | Activity | Status | Notes | |||||||
| 9 | Earthwork | Done? | ask Mike | |||||||
| 10 | Foundation | in progress | ||||||||
| 11 | Steel Erect. | delayed | weather? subcontractor? | |||||||
| 12 | Concrete | #REF! | ||||||||
| 13 | ||||||||||
| 14 | BUDGET | |||||||||
| 15 | Spent to date: | $23,400,000 | ||||||||
| 16 | Budget: | $48,500,000 | see accounting | |||||||
| 17 | Variance: | #VALUE! | ||||||||
| 18 | CPI: | SPI: | WHAT IS CPI? | |||||||
| 19 | ||||||||||
| 20 | LABOR | |||||||||
| 21 | Workers on site: | ~240 | By trade: | |||||||
| 22 | Electricians: | 32? | Ironworkers: | 48 | ||||||
| 23 | Laborers: | see clipboard | ||||||||
| 24 | ||||||||||
| 25 | WEATHER | |||||||||
| 26 | Conditions: | partly cloudy | Delay: | TBD | ||||||
| 27 | ||||||||||
| 28 | PHOTOS | |||||||||
| 29 | See attached (4 photos) | |||||||||
| 30 | (photos not attached) |
Daily ReportBudget (old)Labor LogSheet4 (BROKEN)
📥
POD Ingest Pipeline
Accept Anything. Map Everything.
📂
Drop P6, Excel, PDF, CSV, Photos — any format
📊
Schedule_P6_Export.xer
P6 Schedule · 2.4 MB
💰
Budget_Master_July.xlsx
Excel Budget · 1.8 MB
🔒
Safety_Log_Week28.pdf
PDF Report · 890 KB
👷
Daily_Crew_Roster.csv
CSV Labor · 156 KB
📸
Site_Photos_July15.zip
Photo Archive · 48 MB
🎙️
POD Voice Report
Speak Your Report. AI Does the Rest.
Recording... 0:42
1 / 8
16% Over Budget. On Average.
Most PMs learn at month-end. POD shows you daily.
0:00 / 1:09