Earned Value Analytics

Schedule Says 68%.
Budget Says 81%.
Someone's Lying.

Schedule says 68% complete. Budget says 81% spent. Your PM reports “on track” because they only look at schedule. The controller reports “over budget” because they only look at cost. Neither is wrong. Both are dangerous.

0%
Schedule Complete
0%
Budget Spent
0%
The Disconnect
$0.0M
Hidden Variance

The Cost of Inaction

Every day the disconnect grows, the recovery window shrinks.

$

Schedule and budget live in different tools owned by different people

The scheduler updates Primavera weekly from field walks. The cost engineer updates the ledger monthly from invoices. Neither system talks to the other. You have two competing narratives of project health updated on different cadences with different data.

$

Nobody reconciles schedule and cost until the monthly review

Your PM looks at the schedule and says "on track." Your controller looks at the budget and says "over budget." Both are right about their slice. Neither sees the full picture. The disconnect grows for 30 days before anyone compares the two.

$

CPI and SPI are calculated quarterly, not daily

Earned value metrics require both schedule progress and cost data at the same point in time. When schedule updates weekly and cost updates monthly, your EVM numbers are always stale. By the time CPI drops below 0.90, you have already lost 6 weeks of recovery time.

$

The variance hides in the gap between two reports nobody overlays

Schedule says 68% complete. Budget says 81% spent. The 13-point gap represents $1.2M of hidden variance. But this gap is invisible because the schedule report and cost report are never placed side by side on the same page with the same date.

The Return on POD

Align schedule and budget on the same page, updated from the same field data, every day.

Unified Schedule-Budget View

POD maps daily progress and daily cost to the same timeline from a single voice report. Schedule completion and budget burn are displayed on one chart, updated every day. The gap between the two lines is the variance — visible immediately.

Same-day alignment

Daily CPI and SPI Calculation

Earned value metrics computed every 24 hours instead of every 30 days. When CPI drops from 1.02 to 0.94, you see it on Tuesday — not at the month-end review when the damage is already locked in.

Real-time earned value

Variance Gap Alerts

POD monitors the gap between schedule completion % and budget burn %. When the gap exceeds your threshold (default 5 points), the project team is alerted with the exact dollar value of the disconnect and the activities driving it.

Automatic gap detection

Forecast-at-Completion Intelligence

Using daily CPI and SPI, POD projects EAC (Estimate at Completion) and IEAC (Independent Estimate at Completion) continuously. You always know where the project is heading — not where it was 30 days ago.

Predictive cost projection
Annual Impact With POD
173
KPIs Auto-Calculated
89%
Time Saved
5 min
Voice Report

When Schedule and Budget Diverge

Two tracks that started aligned at project kickoff. By month 8, the gap between schedule completion and budget burn reveals $1.2M of hidden variance that no single report would show.

M1M2M3M4M5M6M7M80%0%ScheduleBudgetSchedule % CompleteBudget % SpentVariance Gap

Schedule-Budget Alignment — Auto-Calculated Daily

These are real POD KPIs. They update every day from a single voice report — no spreadsheet reconciliation required.

Schedule & Budget Performance

SPI 0.00CPI 0.00
25%50%75%100%$0$1.4M$2.7M$4.1M$5.5MM1M2M3M4M5M6M7M8
Planned Progress
Actual Progress
Planned Spend
Actual Spend
SPI0.00
CPI0.00
Sched Var+0.0%
Cost Var+0.0%
Schedule 17.0% behind planbudget 19.7% over target

Schedule Burndown

Remaining (activities)0
Planned (activities)0
Variance+0
0135270405540M1M2M3M4M5M6M7M8
Actual (activities)
Planned
Variance

Earned Value Intelligence

Schedule-Budget Combo Chart

S-curve with histogram overlay showing planned vs actual for both schedule and cost on a single visualization. The divergence between curves tells the story.

AI Schedule Oracle + Budget Sentinel

Two dedicated AI agents watch schedule and cost independently, then cross-reference findings. They detect patterns that single-dimension analysis misses.

Burndown Forecasting

Remaining work and remaining budget on a single burndown chart. When the lines diverge, the project is heading for a cost or schedule overrun — or both.

“Our schedule showed 72% complete. Our budget showed 88% spent. For three months, the scheduler and cost engineer presented to the owner independently — and nobody saw the gap. POD would have shown it on the same chart, the same day, from the same data source. That's the difference between project controls and project theater.”

— Director of Project Controls, $320M Infrastructure Program

Frequently Asked Questions

What's the Gap Between Your Schedule and Budget Right Now?

If your scheduler and cost engineer cannot answer that question with the same number on the same day, your project controls are broken.

Last updated: March 2026