Claims Support

Delay Notices Written
3 Weeks After the Fact

0
Days Avg Notice Delay
0%
% Claims Denied for Late Notice
$0K
K Avg Denied Claim Value
0
Min With POD

The Challenge

Notices written weeks after events

Your contract requires delay notices within 7 days. Your team writes them 3 weeks later when the PM finally has time. By then the contractual deadline has passed.

No contemporaneous records

The delay notice references events from 3 weeks ago. The daily report from that day says sunny, 45 workers, normal operations. There is nothing linking the event to the impact.

67% of claims denied for late notice

Most construction contracts have strict notice provisions. Fail to notify within the window and you waive the right to claim regardless of merit.

Impact quantification is guesswork

How many crew hours were lost? Which activities were impacted? What was the critical path effect? Without daily data, impact analysis is opinion not fact.

The POD Solution Path

1

Voice-capture delay events

Rain started at 10 AM, concrete crew sent home, 47 manhours lost. Speak the delay event and POD documents it with timestamp and impact data.

Same-day documentation
2

Auto-generated delay notices

POD drafts the formal delay notice from your voice report, linking it to the daily report, weather data, and affected activities. Send it within hours.

Timely notices
3

Impact quantification

POD calculates lost manhours, affected activities, and schedule impact from daily data. Your delay claim has quantified damages, not estimates.

Quantified impact
4

Claims support package

Export a complete delay claim package: daily reports, weather data, manpower records, schedule analysis, and contemporaneous documentation.

Defensible claims

Claims Intelligence

Delay Event Registry

Every delay event documented with cause, impact, duration, and affected activities. Full audit trail.

Notice Deadline Tracking

Contractual notice periods tracked automatically. Never miss a filing deadline again.

Impact Quantification

Automatic calculation of manhours lost, schedule impact, and cost implications from daily data.

“We lost a $500K delay claim because our notice was 18 days late. The contract required 7 days. With POD the delay notice auto-generated the same day the event occurred.”

— Claims Manager, Infrastructure Contractor

Live Demo

Your Schedule and Budget — In Two Gauges

POD tracks hundreds of KPIs from a 5-minute voice report. Here are just 2 of them.

Dual EVM Gauge

Earned Value Performance

Cost Performance
0.71.3
0.70
Performance
Critical
0.49CPI × SPI
Schedule Performance
0.71.3
0.70
Performance
Critical

Both cost and schedule under pressure

CPI
0.70
SPI
0.70
Cost Var-30.0%
Sched Var-30.0%
Composite0.490
EAC Factor1.429
BudgetOver Budget
ScheduleBehind
HealthAction Needed
PODProject DNA

Project DNA

POD
Construction
0HEALTH
Schedule0
Budget0
Safety0
Quality0
Resources0
Health0
Strongest0
Weakest0
Safety (95) leads, Resources (79) needs focus

These update in real time from a 5-minute voice report. No spreadsheets. No data entry.

Frequently Asked Questions

Never Lose a Delay Claim to Late Notice

See how POD turns daily reports into defensible delay documentation.

Last updated: February 2026