Construction billing methods.Six contracts. One pay app.
A 2026 reference for lump sum, unit price, T&M, cost-plus, GMP, and CMAR contracts. AIA G702 and G703 walkthrough, retainage rules, change-order pricing, and state Prompt Payment Acts.
Construction projects bill under six primary contract methods: lump sum (fixed price), unit price, time and materials, cost-plus, guaranteed maximum price (GMP), and construction manager at risk (CMAR). Each method allocates price risk differently between owner and contractor. Most progress invoicing uses the AIA G702 Application and Certificate for Payment paired with the G703 Continuation Sheet, which breaks the contract sum into Schedule of Values line items and tracks percent complete, retainage, and balance to finish each period. State Prompt Payment Acts cap how long owners can hold payment after approval, typically 7 to 30 days.
The six primary construction billing methods
The choice of billing method determines who carries price risk, how change orders get priced, and what documentation each invoice requires. Most public-bid commercial work is lump sum. Most negotiated commercial work is GMP. Most civil and heavy-highway work is unit price. T&M and cost-plus fill the gaps where scope is undefined.
Lump Sum
Risk: ContractorLump Sum (Fixed Price)
- When used
- Fully designed projects with clear scope. Most commercial and public-bid work.
- Pros
- Cost certainty for owner. Simple administration. Encourages efficiency.
- Cons
- Less flexibility for design changes. Contingencies are buried in the price.
Unit Price
Risk: Owner (quantities)Unit Price
- When used
- Civil and earthwork. Highway and infrastructure where quantities are estimates.
- Pros
- Fair price for unknown quantities. Owner pays only for work performed.
- Cons
- Total cost is unknown at bid. Quantity disputes are common.
T&M
Risk: Owner (scope)Time and Materials (T&M)
- When used
- Repair, emergency work, change-order work, and projects with undefined scope.
- Pros
- Flexibility. Easy to start without complete documents.
- Cons
- No cost ceiling. Requires daily timesheet and material backup.
Cost-Plus
Risk: Owner (all)Cost-Plus
- When used
- Early-stage design-build, fast-track projects, custom residential.
- Pros
- Maximum flexibility. Open-book transparency. Aligns owner-contractor incentives.
- Cons
- Owner takes price risk. Requires trust and detailed cost auditing.
GMP
Risk: HybridGuaranteed Maximum Price (GMP)
- When used
- Design-build, CM-at-risk delivery, complex commercial. Most negotiated work.
- Pros
- Cost ceiling for owner. Cost-plus flexibility below ceiling. Shared savings.
- Cons
- Contractor builds contingency into GMP. Complex change-order accounting.
CMAR
Risk: CM holds GMPConstruction Manager at Risk (CMAR)
- When used
- Public agencies, healthcare, higher education, large institutional projects.
- Pros
- Preconstruction expertise. Owner-CM-architect collaboration. GMP cost cap.
- Cons
- Higher CM fee. Preconstruction services are billed separately.
AIA G702 and G703: the standard payment application
The American Institute of Architects (AIA) G702 Application and Certificate for Payment is the most widely-used progress invoice form in U.S. construction. It is a single page summarizing nine lines of payment math. The G703 Continuation Sheet is the line-item backup, breaking the contract into individual Schedule of Values items and tracking each one column by column.
| Col | Label | Description |
|---|---|---|
| A | Item No. | Sequential line number. |
| B | Description | Trade or work item description matching the Schedule of Values. |
| C | Scheduled Value | Total contract value allocated to this line item. |
| D | Previous Periods | Cumulative work completed and billed in prior payment applications. |
| E | This Period | Work completed and being billed in the current payment application. |
| F | Materials Stored | Value of materials delivered and stored but not yet incorporated into work. |
| G | Total Completed and Stored | Sum of columns D + E + F. |
| H | Percent Complete | Column G divided by Column C, expressed as a percentage. |
| I | Balance to Finish | Column C minus Column G. Remaining contract value for this line. |
| J | Retainage | Amount withheld this period for this line (typically 5 to 10 percent of G). |
How to fill out an AIA G702 and G703
Five steps. Same structure every month. The G703 is filled out first, then totals are carried to the G702 summary page. The architect or owners representative certifies the requested amount.
- 1
Update the G703 Continuation Sheet
Walk line by line through the approved Schedule of Values.
For each SOV line, fill Column D with cumulative work billed in prior applications, Column E with work completed in the current period, and Column F with the value of materials properly delivered and stored either on site or in a bonded offsite location. Be conservative on Column E claims; under-billing is easier to correct than overbilling, which can trigger architect adjustments and Stop-Work Notices in some contract forms.
- 2
Calculate completion and balances
Sum, divide, and subtract to produce Columns G, H, and I.
Column G is D + E + F. Column H is G divided by C, written as a percentage. Column I is C minus G, the remaining contract value for the line. Owners scrutinize Column H closely. A foundation line showing 95 percent complete in month two when the slab has not been poured is a front-loading signal that invites a back-charge audit.
- 3
Apply retainage per line
Withhold the contracted retainage percentage on Column G.
Column J retainage is typically 5 to 10 percent of Column G per line. Sum Column J at the bottom of the G703 to produce the total retainage carried to the G702 Line 5. Some contracts reduce retainage to zero after 50 percent project completion, or release retainage on early-completing line items (so-called retainage release on substantial completion of a defined scope).
- 4
Complete the G702 summary
Carry G703 totals to the G702 nine-line payment summary.
G702 Line 1 is the original contract sum. Line 2 is net change by approved change orders. Line 3 is the contract sum to date (Line 1 + Line 2). Line 4 is total completed and stored to date (G703 Column G total). Line 5 is retainage. Line 6 is total earned less retainage (Line 4 minus Line 5). Line 7 is less previous certificates for payment. Line 8 is current payment due. Line 9 is the balance to finish including retainage.
- 5
Sign, certify, and submit
Contractor signs first. Architect certifies second.
The contractor signs the certification block attesting the work has been completed in accordance with the contract documents and that all sums previously paid have been used to pay for work, labor, and materials. The architect or owner reviews, may adjust the certified amount downward, and signs the architects certification block. Per A201 General Conditions 9.6.1, the owner must pay the certified amount within seven days after issuance.
Worked example: $2.4M lump sum, month 6
A mid-size general contractor on a $2,400,000 lump sum commercial project. Eight Schedule of Values line items. Month 6 of construction, with structural steel and roofing in active work. 5 percent retainage. ACH payment, net 30.
| Item | C: Value | D: Prev | E: This | F: Stored | H: % |
|---|---|---|---|---|---|
| General Conditions | $240,000 | $100,000 | $20,000 | $0 | 50% |
| Sitework and Earthwork | $280,000 | $280,000 | $0 | $0 | 100% |
| Concrete and Foundations | $360,000 | $360,000 | $0 | $0 | 100% |
| Structural Steel | $480,000 | $384,000 | $72,000 | $0 | 95% |
| Roofing and Envelope | $320,000 | $80,000 | $96,000 | $24,000 | 63% |
| Mechanical and Electrical | $420,000 | $84,000 | $105,000 | $42,000 | 55% |
| Interior Finishes | $240,000 | $0 | $24,000 | $12,000 | 15% |
| Closeout and Commissioning | $60,000 | $0 | $0 | $0 | 0% |
This period the contractor completed $395,000 of new work and stored materials. After 5 percent retainage and crediting prior payments, current payment due is $375,250. Balance to finish including retainage is $801,150. Under most state Prompt Payment Acts, the owner must pay within 30 days of architect certification.
Retainage, Schedule of Values, and change orders
Three concepts surface on every monthly invoice regardless of contract method: the retainage withheld, the Schedule of Values that anchors the G703, and any change orders that adjust the contract sum.
Retainage
Typically 5 to 10 percent withheld from each progress payment. Partial release at substantial completion, balance at final completion. Many states cap retainage at 5 or 10 percent and require reduction or release on milestones. Federal projects under FAR Part 32 use 10 percent until satisfactory progress is established.
Schedule of Values
The contract price broken into line items, cost-loaded against the project schedule. More line items mean granular tracking but more change-order accounting. Owners reject front-loaded SOVs that shift cash risk. Approval happens before the first payment application.
Change Orders
AIA A201 Section 7.3.3 allows four pricing methods: lump sum, unit price, cost plus fee, or another method agreed upon. The Eichleay formula calculates unabsorbed home office overhead damages on owner-caused delays. Approved change orders flow to G702 Line 2.
Six mistakes that delay construction payments
These show up in nearly every payment-application audit. Each one either delays the certified amount, triggers a back-charge, or leaves money on the table at closeout.
- 01
Front-loading the Schedule of Values
Assigning higher values to early line items (mobilization, demolition, foundations) to recover cash sooner. Owners and architects scrutinize SOVs for front-loading because it shifts financial risk to the owner if the contractor walks off mid-project. Most contracts require unbalanced SOVs to be flagged and rejected at SOV approval.
- 02
Forgetting to track retainage release at substantial completion
Retainage is withheld throughout the project. At substantial completion, a partial release is typical (often half), with the balance released at final completion. Contractors who do not track retainage by line item find themselves chasing release of $50,000 or more six months after move-in.
- 03
Wrong markup calculation on cost-plus and T&M billings
Cost-plus contracts define which costs are markup-eligible (direct labor, materials, subcontracts) and which are not (home office overhead, project management, certain equipment). Marking up an excluded cost is the most common source of cost-plus audit disputes. Read the cost definition section before invoicing.
- 04
Missing the state Prompt Payment Act deadline
Most states require payment within 7 to 30 days of an approved invoice. If the owner is late, the contractor is entitled to statutory interest (typically 1 percent per month) and may suspend performance after notice. Contractors who do not invoke their rights leave money on the table.
- 05
Billing for materials stored offsite without the right documentation
Materials stored offsite require: (1) proper insurance with the owner as additional insured, (2) title transfer upon payment, (3) bonded storage or segregation, and (4) evidence of payment to the supplier. Missing any of these gets Column F of the G703 rejected, and the contractor finances the materials until they reach the site.
- 06
Not pricing change orders correctly under the contract method
AIA A201 Section 7.3.3 defines four allowable change-order pricing methods: lump sum, unit price, cost plus fee, or another method agreed upon. Pricing a change order by the wrong method (using cost-plus when the contract requires unit pricing) gives the owner grounds to reject or negotiate down.
State Prompt Payment Acts
Most states cap the time an owner can hold approved invoices and impose statutory interest for late payment. Subcontractor pay-when-paid clauses are enforceable but cannot indefinitely defer payment. Five representative states below; consult your specific state statute before suspending performance.
| State | Private Projects | Public Projects | Interest | Statute |
|---|---|---|---|---|
| California | 30 days | 30 days | 2% per month | Civil Code 8800, Public Contract Code 7107 |
| Florida | 14 days | 20 days | 1% per month or contract rate | Fla. Stat. 715.12, 218.74 |
| New York | 30 days | 30 days | 1% per month | General Business Law 756-a, State Finance Law 139-f |
| Texas | 35 days | 31 days | 1.5% per month | Property Code 28.002, Government Code 2251 |
| Illinois | 15 days approval + 15 days pay | 60 days | 10% per annum | 770 ILCS 60/0.01, 50 ILCS 505/1 |
Frequently asked questions
Most contractors assemble the G702 and G703 in a spreadsheet, copy and paste from last months file, and hope nobody notices the percent-complete column drifted from the daily reports. The Schedule of Values lives in one tool, daily labor and material data lives in another, change orders live in email, and retainage release is tracked on a sticky note. Plan of Day is voice-first construction reporting that captures daily labor hours, materials installed, and stored material counts in the field, then routes that data through POD's intelligence engine into the line items that drive monthly payment applications. The G702 and G703 stay current automatically. Specialized AI agents flag front-loaded SOVs, missed retainage releases, and Prompt Payment Act deadlines before the architect catches them.
Further reading
Earned Value Management for Construction
How CPI and SPI relate to payment-application percent-complete. EVM data sources, formulas, and forecasting.
Construction Daily Report Guide
How daily report fields (labor hours, materials installed, equipment on site) feed into G703 line-item billing.
What to Include in a Construction Daily Report
The labor and material backup data that supports payment applications and cost-plus invoicing.
Plan of Day vs Daily Log
Forward-looking planning versus retrospective documentation. Why both matter for monthly billing cycles.
Sources
- AIA Contract Documents — A201 General Conditions, A101 Standard Form Agreement, G702 Application and Certificate for Payment, G703 Continuation Sheet.
- ConsensusDocs — ConsensusDocs 200 Owner-Contractor Agreement and ConsensusDocs 290 Multi-Family Form. Industry-coalition standard contracts.
- AACE International — Recommended Practice 84R-13 Planning and Accounting for Adverse Weather and related cost-engineering RPs.
- FAR Part 32 (Contract Financing) — Federal Acquisition Regulation rules for progress payments, retainage, and contract financing on federal projects.
- FHWA Federal-Aid Project Contract Administration — Unit-price contracting, measurement and payment, and federal-aid prompt payment requirements.
- State Prompt Payment Acts cited: California Civil Code 8800 and Public Contract Code 7107; Florida Statutes 715.12 and 218.74; New York General Business Law 756-a and State Finance Law 139-f; Texas Property Code 28.002 and Government Code 2251; Illinois 770 ILCS 60/0.01 and 50 ILCS 505/1.
- Associated General Contractors of America (AGC) — Industry guidance on payment-application practices, change-order administration, and Eichleay formula application.