Back online
Definitive Guide

Construction billing methods.Six contracts. One pay app.

A 2026 reference for lump sum, unit price, T&M, cost-plus, GMP, and CMAR contracts. AIA G702 and G703 walkthrough, retainage rules, change-order pricing, and state Prompt Payment Acts.

0.0
Primary Billing Methods
0
G703 Column Fields
0.0%
Typical Retainage
0
Days Prompt Payment
Direct Answer

Construction projects bill under six primary contract methods: lump sum (fixed price), unit price, time and materials, cost-plus, guaranteed maximum price (GMP), and construction manager at risk (CMAR). Each method allocates price risk differently between owner and contractor. Most progress invoicing uses the AIA G702 Application and Certificate for Payment paired with the G703 Continuation Sheet, which breaks the contract sum into Schedule of Values line items and tracks percent complete, retainage, and balance to finish each period. State Prompt Payment Acts cap how long owners can hold payment after approval, typically 7 to 30 days.

The six primary construction billing methods

The choice of billing method determines who carries price risk, how change orders get priced, and what documentation each invoice requires. Most public-bid commercial work is lump sum. Most negotiated commercial work is GMP. Most civil and heavy-highway work is unit price. T&M and cost-plus fill the gaps where scope is undefined.

Lump Sum

Risk: Contractor

Lump Sum (Fixed Price)

When used
Fully designed projects with clear scope. Most commercial and public-bid work.
Pros
Cost certainty for owner. Simple administration. Encourages efficiency.
Cons
Less flexibility for design changes. Contingencies are buried in the price.

Unit Price

Risk: Owner (quantities)

Unit Price

When used
Civil and earthwork. Highway and infrastructure where quantities are estimates.
Pros
Fair price for unknown quantities. Owner pays only for work performed.
Cons
Total cost is unknown at bid. Quantity disputes are common.

T&M

Risk: Owner (scope)

Time and Materials (T&M)

When used
Repair, emergency work, change-order work, and projects with undefined scope.
Pros
Flexibility. Easy to start without complete documents.
Cons
No cost ceiling. Requires daily timesheet and material backup.

Cost-Plus

Risk: Owner (all)

Cost-Plus

When used
Early-stage design-build, fast-track projects, custom residential.
Pros
Maximum flexibility. Open-book transparency. Aligns owner-contractor incentives.
Cons
Owner takes price risk. Requires trust and detailed cost auditing.

GMP

Risk: Hybrid

Guaranteed Maximum Price (GMP)

When used
Design-build, CM-at-risk delivery, complex commercial. Most negotiated work.
Pros
Cost ceiling for owner. Cost-plus flexibility below ceiling. Shared savings.
Cons
Contractor builds contingency into GMP. Complex change-order accounting.

CMAR

Risk: CM holds GMP

Construction Manager at Risk (CMAR)

When used
Public agencies, healthcare, higher education, large institutional projects.
Pros
Preconstruction expertise. Owner-CM-architect collaboration. GMP cost cap.
Cons
Higher CM fee. Preconstruction services are billed separately.

AIA G702 and G703: the standard payment application

The American Institute of Architects (AIA) G702 Application and Certificate for Payment is the most widely-used progress invoice form in U.S. construction. It is a single page summarizing nine lines of payment math. The G703 Continuation Sheet is the line-item backup, breaking the contract into individual Schedule of Values items and tracking each one column by column.

ColLabelDescription
AItem No.Sequential line number.
BDescriptionTrade or work item description matching the Schedule of Values.
CScheduled ValueTotal contract value allocated to this line item.
DPrevious PeriodsCumulative work completed and billed in prior payment applications.
EThis PeriodWork completed and being billed in the current payment application.
FMaterials StoredValue of materials delivered and stored but not yet incorporated into work.
GTotal Completed and StoredSum of columns D + E + F.
HPercent CompleteColumn G divided by Column C, expressed as a percentage.
IBalance to FinishColumn C minus Column G. Remaining contract value for this line.
JRetainageAmount withheld this period for this line (typically 5 to 10 percent of G).

How to fill out an AIA G702 and G703

Five steps. Same structure every month. The G703 is filled out first, then totals are carried to the G702 summary page. The architect or owners representative certifies the requested amount.

  1. 1

    Update the G703 Continuation Sheet

    Walk line by line through the approved Schedule of Values.

    For each SOV line, fill Column D with cumulative work billed in prior applications, Column E with work completed in the current period, and Column F with the value of materials properly delivered and stored either on site or in a bonded offsite location. Be conservative on Column E claims; under-billing is easier to correct than overbilling, which can trigger architect adjustments and Stop-Work Notices in some contract forms.

  2. 2

    Calculate completion and balances

    Sum, divide, and subtract to produce Columns G, H, and I.

    Column G is D + E + F. Column H is G divided by C, written as a percentage. Column I is C minus G, the remaining contract value for the line. Owners scrutinize Column H closely. A foundation line showing 95 percent complete in month two when the slab has not been poured is a front-loading signal that invites a back-charge audit.

  3. 3

    Apply retainage per line

    Withhold the contracted retainage percentage on Column G.

    Column J retainage is typically 5 to 10 percent of Column G per line. Sum Column J at the bottom of the G703 to produce the total retainage carried to the G702 Line 5. Some contracts reduce retainage to zero after 50 percent project completion, or release retainage on early-completing line items (so-called retainage release on substantial completion of a defined scope).

  4. 4

    Complete the G702 summary

    Carry G703 totals to the G702 nine-line payment summary.

    G702 Line 1 is the original contract sum. Line 2 is net change by approved change orders. Line 3 is the contract sum to date (Line 1 + Line 2). Line 4 is total completed and stored to date (G703 Column G total). Line 5 is retainage. Line 6 is total earned less retainage (Line 4 minus Line 5). Line 7 is less previous certificates for payment. Line 8 is current payment due. Line 9 is the balance to finish including retainage.

  5. 5

    Sign, certify, and submit

    Contractor signs first. Architect certifies second.

    The contractor signs the certification block attesting the work has been completed in accordance with the contract documents and that all sums previously paid have been used to pay for work, labor, and materials. The architect or owner reviews, may adjust the certified amount downward, and signs the architects certification block. Per A201 General Conditions 9.6.1, the owner must pay the certified amount within seven days after issuance.

Worked example: $2.4M lump sum, month 6

A mid-size general contractor on a $2,400,000 lump sum commercial project. Eight Schedule of Values line items. Month 6 of construction, with structural steel and roofing in active work. 5 percent retainage. ACH payment, net 30.

ItemC: ValueD: PrevE: ThisF: StoredH: %
General Conditions$240,000$100,000$20,000$050%
Sitework and Earthwork$280,000$280,000$0$0100%
Concrete and Foundations$360,000$360,000$0$0100%
Structural Steel$480,000$384,000$72,000$095%
Roofing and Envelope$320,000$80,000$96,000$24,00063%
Mechanical and Electrical$420,000$84,000$105,000$42,00055%
Interior Finishes$240,000$0$24,000$12,00015%
Closeout and Commissioning$60,000$0$0$00%
G702 Summary
Line 3: Contract sum to date
$2,400,000
Line 4: Total completed and stored
$1,683,000
Line 5: Retainage held (5%)
$84,150
Line 6: Total earned less retainage
$1,598,850
Line 7: Less previous payments
$1,223,600
Line 8: Current payment due
$375,250

This period the contractor completed $395,000 of new work and stored materials. After 5 percent retainage and crediting prior payments, current payment due is $375,250. Balance to finish including retainage is $801,150. Under most state Prompt Payment Acts, the owner must pay within 30 days of architect certification.

Retainage, Schedule of Values, and change orders

Three concepts surface on every monthly invoice regardless of contract method: the retainage withheld, the Schedule of Values that anchors the G703, and any change orders that adjust the contract sum.

Retainage

Typically 5 to 10 percent withheld from each progress payment. Partial release at substantial completion, balance at final completion. Many states cap retainage at 5 or 10 percent and require reduction or release on milestones. Federal projects under FAR Part 32 use 10 percent until satisfactory progress is established.

Schedule of Values

The contract price broken into line items, cost-loaded against the project schedule. More line items mean granular tracking but more change-order accounting. Owners reject front-loaded SOVs that shift cash risk. Approval happens before the first payment application.

Change Orders

AIA A201 Section 7.3.3 allows four pricing methods: lump sum, unit price, cost plus fee, or another method agreed upon. The Eichleay formula calculates unabsorbed home office overhead damages on owner-caused delays. Approved change orders flow to G702 Line 2.

Six mistakes that delay construction payments

These show up in nearly every payment-application audit. Each one either delays the certified amount, triggers a back-charge, or leaves money on the table at closeout.

  1. 01

    Front-loading the Schedule of Values

    Assigning higher values to early line items (mobilization, demolition, foundations) to recover cash sooner. Owners and architects scrutinize SOVs for front-loading because it shifts financial risk to the owner if the contractor walks off mid-project. Most contracts require unbalanced SOVs to be flagged and rejected at SOV approval.

  2. 02

    Forgetting to track retainage release at substantial completion

    Retainage is withheld throughout the project. At substantial completion, a partial release is typical (often half), with the balance released at final completion. Contractors who do not track retainage by line item find themselves chasing release of $50,000 or more six months after move-in.

  3. 03

    Wrong markup calculation on cost-plus and T&M billings

    Cost-plus contracts define which costs are markup-eligible (direct labor, materials, subcontracts) and which are not (home office overhead, project management, certain equipment). Marking up an excluded cost is the most common source of cost-plus audit disputes. Read the cost definition section before invoicing.

  4. 04

    Missing the state Prompt Payment Act deadline

    Most states require payment within 7 to 30 days of an approved invoice. If the owner is late, the contractor is entitled to statutory interest (typically 1 percent per month) and may suspend performance after notice. Contractors who do not invoke their rights leave money on the table.

  5. 05

    Billing for materials stored offsite without the right documentation

    Materials stored offsite require: (1) proper insurance with the owner as additional insured, (2) title transfer upon payment, (3) bonded storage or segregation, and (4) evidence of payment to the supplier. Missing any of these gets Column F of the G703 rejected, and the contractor finances the materials until they reach the site.

  6. 06

    Not pricing change orders correctly under the contract method

    AIA A201 Section 7.3.3 defines four allowable change-order pricing methods: lump sum, unit price, cost plus fee, or another method agreed upon. Pricing a change order by the wrong method (using cost-plus when the contract requires unit pricing) gives the owner grounds to reject or negotiate down.

State Prompt Payment Acts

Most states cap the time an owner can hold approved invoices and impose statutory interest for late payment. Subcontractor pay-when-paid clauses are enforceable but cannot indefinitely defer payment. Five representative states below; consult your specific state statute before suspending performance.

StatePrivate ProjectsPublic ProjectsInterestStatute
California30 days30 days2% per monthCivil Code 8800, Public Contract Code 7107
Florida14 days20 days1% per month or contract rateFla. Stat. 715.12, 218.74
New York30 days30 days1% per monthGeneral Business Law 756-a, State Finance Law 139-f
Texas35 days31 days1.5% per monthProperty Code 28.002, Government Code 2251
Illinois15 days approval + 15 days pay60 days10% per annum770 ILCS 60/0.01, 50 ILCS 505/1

Frequently asked questions

Lump sum is a single fixed price for the entire scope of work; the contractor takes the price risk. Cost-plus reimburses the contractor for actual costs plus a fee (fixed or percentage); the owner takes the price risk. Lump sum is typical for fully-designed projects with clear scope. Cost-plus is typical when scope is undefined or the owner wants design-build flexibility.

AIA G702 is the Application and Certificate for Payment, a single-page form summarizing the contractors payment request for the current period. AIA G703 is the Continuation Sheet that breaks down the request line-by-line against the Schedule of Values, showing scheduled value, previous work, current work, materials stored, percent complete, balance to finish, and retainage withheld per line item.

A GMP contract is open-book cost-plus billing with a ceiling. The owner reimburses actual costs plus a fee, but the contractor guarantees the total will not exceed a maximum price. Cost savings below the GMP are typically shared between owner and contractor per a defined formula. GMP is the standard delivery model for Construction Manager at Risk (CMAR) projects.

Retainage is typically 5 to 10 percent withheld from each progress payment, released at substantial completion (partial) and final completion (balance). Many states cap retainage at 5 or 10 percent by statute; some reduce retainage to zero after 50 percent project completion. Federal projects under FAR Part 32 use 10 percent until satisfactory progress is established.

A Schedule of Values is the cost breakdown of the contract price into individual line items, typically aligned with the project schedule. The SOV is the foundation of every G703 continuation sheet. More line items mean more granular billing visibility but more change-order tracking burden. The owner approves the SOV before the first payment application.

Front-loading is assigning higher values to early line items (mobilization, demolition, foundations) to recover cash sooner. Owners and architects scrutinize SOVs for front-loading because it shifts financial risk to the owner if the contractor walks off mid-project. Most contracts require unbalanced SOVs to be flagged and rejected during the approval phase.

The Eichleay formula calculates unabsorbed home office overhead damages when an owner-caused delay extends the project. It allocates a daily home office overhead rate to the delay period based on the ratio of the contract billings to total company billings during the original performance period. Federal courts accept Eichleay; state courts apply it inconsistently.

Most states mandate payment within 7 to 30 days of an approved invoice, with interest penalties for late payment. California requires payment within 30 days (Civil Code 8800), Florida within 14 days for private projects (Florida Statute 715.12), New York within 30 days (General Business Law 756-a), Texas within 35 days for private and 31 days for public (Property Code 28.002, Government Code 2251). Subcontractor pay-when-paid clauses are enforceable but cannot indefinitely extend the deadline.

Progress billing invoices monthly based on percent complete per line item against the Schedule of Values. Milestone billing invoices when defined project events occur (foundation complete, framing complete, substantial completion). Progress billing is the default for most commercial construction. Milestone billing is common for residential and federal fixed-price contracts.

Yes, but most contracts require: (1) materials are properly insured, (2) title is transferred to the owner upon payment, (3) materials are stored in a bonded warehouse or otherwise segregated, and (4) the contractor provides evidence of payment to the supplier. AIA G703 column F captures offsite-stored material value separately from work-in-place.

When POD is the natural answer

Most contractors assemble the G702 and G703 in a spreadsheet, copy and paste from last months file, and hope nobody notices the percent-complete column drifted from the daily reports. The Schedule of Values lives in one tool, daily labor and material data lives in another, change orders live in email, and retainage release is tracked on a sticky note. Plan of Day is voice-first construction reporting that captures daily labor hours, materials installed, and stored material counts in the field, then routes that data through POD's intelligence engine into the line items that drive monthly payment applications. The G702 and G703 stay current automatically. Specialized AI agents flag front-loaded SOVs, missed retainage releases, and Prompt Payment Act deadlines before the architect catches them.

Sources

  • AIA Contract Documents — A201 General Conditions, A101 Standard Form Agreement, G702 Application and Certificate for Payment, G703 Continuation Sheet.
  • ConsensusDocs — ConsensusDocs 200 Owner-Contractor Agreement and ConsensusDocs 290 Multi-Family Form. Industry-coalition standard contracts.
  • AACE International — Recommended Practice 84R-13 Planning and Accounting for Adverse Weather and related cost-engineering RPs.
  • FAR Part 32 (Contract Financing) — Federal Acquisition Regulation rules for progress payments, retainage, and contract financing on federal projects.
  • FHWA Federal-Aid Project Contract Administration — Unit-price contracting, measurement and payment, and federal-aid prompt payment requirements.
  • State Prompt Payment Acts cited: California Civil Code 8800 and Public Contract Code 7107; Florida Statutes 715.12 and 218.74; New York General Business Law 756-a and State Finance Law 139-f; Texas Property Code 28.002 and Government Code 2251; Illinois 770 ILCS 60/0.01 and 50 ILCS 505/1.
  • Associated General Contractors of America (AGC) — Industry guidance on payment-application practices, change-order administration, and Eichleay formula application.
Last updated: May 2026