CommittedCost

The overrun is locked in the day the contract is signed, not the day the invoice arrives. Committed cost is the warning that comes months before the money moves.

Definition

Committed cost is the value the project is contractually obligated to spend under signed subcontracts, issued purchase orders, and executed change orders. It sits between the budget, what you planned to spend, and the actual cost, what you have paid, with the portion not yet invoiced being the open commitment. Watching committed cost against the budget is how a team sees an overrun coming before the invoices arrive.

Between the plan and the payment

On our $10.8M cost budget, $5.4M is paid and another $2.6M is committed but not yet invoiced, an $8.0M total obligation. The committed line, not the paid line, is what tells you whether the budget still holds.

Cost budget $10.8MActual $5.4MOpen $2.6MuncommittedCommitted total $8.0M

Three readings of the same line

Budget, committed, actual: the plan, the obligation, and the reality. The gap between committed and budget is the overrun you can still do something about.

ReadingAnswersTiming
BudgetWhat the estimate said it should costSet at award
Committed costWhat signed contracts + POs bind you toAt each award, before invoices
Actual costWhat has actually been paidAs invoices land

The budget-minus-committed gap at award is the buy-out buffer; the remaining spend is cost to complete.

How POD reads committed cost

POD reads each purchase order, subcontract, and executed change order as committed cost against the budget line it belongs to, and reconciles it alongside the actual cost from your pay applications, so the budget, the committed total, and the paid-to-date figure sit together instead of in three separate systems. A category whose committed cost has crossed its budget is visible at award, next to the field record, rather than at month-end close. POD reads and reconciles the commitments you upload; it does not negotiate your contracts or decide how to cover an overrun. What it removes is the lag between signing a commitment and seeing its effect on the budget.

Budget vs committed cost guide

Frequently asked questions

What is left to spend is the forecast

Committed minus actual is work bought but not yet paid. Add the still-uncommitted scope and you have the cost to complete.