Construction Project ControlsGlossary
A working glossary of the construction project-controls terms teams use on real jobs, from earned value and pay applications to change orders, scheduling, and field quality. Each entry is written to answer the question, not pad a definition: what the term means, why it matters on site, and how it is calculated or used.
Earned Value & Project Controls
The cost-and-schedule performance language: EVM, CPI, SPI, the baseline, and the forecasts built on them.
Percent Complete
The fraction of work done that drives earned value, and the measurement methods (units, milestone, 0/100, 50/50, cost ratio) that decide it.
Certified vs Pending Claim (Pay Application)
A submitted pay application is a pending claim; a certified one has been approved for payment. The number is the same, the label and the record are not.
Cost Performance Index (CPI) & Cost Variance
The cost reading of earned value: CPI = EV/AC and CV = EV−AC tell you whether each dollar is buying the work it should.
Estimate at Completion (EAC, ETC, VAC)
The forecast of final cost (EAC), the cost of the work still left (ETC), and the projected overrun or underrun (VAC), with the four EAC formulas.
Earned Schedule (ES)
The time-based schedule reading that fixes classic SPI: it measures the lag in weeks, not dollars, and stays honest right to the finish.
Earned Value Management (EVM)
The project-controls method that measures cost and schedule performance together, from planned value, earned value, and actual cost.
Of-Record EVM
The one sealed, dated set of earned-value figures a project treats as authoritative, and the rule for which snapshot wins when several exist.
Period Close
The dated cut that seals a period’s progress and cost to one as-of date, so earned value is measured from a fixed record instead of a moving feed.
Performance Measurement Baseline (PMB)
The frozen, time-phased budget, organized into control accounts, that earned value measures against. Management reserve sits outside it.
Planned Value, Earned Value & Actual Cost
The three measurements earned value is built on (also BCWS, BCWP, ACWP): what was planned, what is done, and what it cost.
Construction S-Curve
The cumulative cost-or-progress curve over time. Plot planned, earned, and actual together and the gaps become the variances.
Schedule Performance Index (SPI) & Variance
The schedule reading of earned value: SPI = EV/PV and SV = EV−PV measure pace against plan, in dollars rather than days.
To-Complete Performance Index (TCPI)
The cost efficiency the remaining work must hit to still land on budget. Compared to the current CPI, it is the reality check on the target.
Billing & Pay Applications
How work gets billed and paid: the schedule of values, pay applications, retainage, and lien waivers.
AIA Pay Application (G702 / G703)
The standard construction progress payment request: a G702 summary certificate backed by a G703 line-item continuation sheet that reconcile to each other.
Lien Waiver
A signed release of the right to lien the property in exchange for payment. Four forms from two axes: conditional vs unconditional, progress vs final.
LNTP & Mobilization
A limited notice authorizes early work before the full contract; mobilization is the up-front money to start, recovered across billings so it never outruns work in place.
Work Completed & Net Amount Due
The pay-app arithmetic: work completed plus stored materials, less retainage and prior payments, equals the net check for the period.
Over- and Under-Billing
The gap between what has been billed and what has been earned. Overbilled is a balance-sheet liability; underbilled is an asset. Tracked on the WIP schedule.
Retainage
The 5-10% withheld from each progress payment until the work is complete. It accrues in a running balance and is released near the end of the job.
Schedule of Values (SOV)
The line-item breakdown of the contract sum. Every scope gets a dollar value, the lines sum to the contract, and each pay application bills against them.
Change Management & Commercial
The records that govern scope, questions, and disputes: RFIs, change orders, NCRs, claims, and notices.
Allowance
A placeholder sum for scope whose price is not yet known. The difference between the allowance and the actual selection is reconciled by change order, up or down.
Buy-Out
Awarding subcontracts and POs at committed prices early. The gap between budgeted and committed becomes a buy-out buffer that absorbs overruns before contingency.
Construction Claims & Back Charges
A claim is a formal demand for added cost or time; a back charge deducts costs one party owes another. Both are won or lost on the project record.
Change Order (CO)
A written amendment to the contract that changes scope, price, or time. Signed by the parties, it formally revises what was agreed.
Compensable vs Non-Compensable Delay
Both are excusable, but only one carries money. Owner-caused delay is compensable (time and cost recovery); a neutral event is non-compensable (a time extension only).
Contingency
Budgeted money for known risks inside the current scope, drawn down as those risks retire. Distinct from management reserve, and it should burn down with the risk, not the calendar.
Excusable Delay
A delay beyond the contractor's control that earns a time extension. It splits into compensable (owner-caused: time and money) and non-compensable (neutral events: time only).
Force Majeure
The clause covering extraordinary events beyond either party's control. As a delay it is usually excusable but non-compensable: a time extension, no money, and no liquidated damages.
Liquidated Damages (LDs)
A fixed daily sum the contractor owes for finishing late on a non-excusable delay. It must be a genuine pre-estimate of the owner's loss, not an unenforceable penalty.
Non-Conformance Report (NCR)
The formal record raised when work, material, or a process fails to meet the specification, carrying its disposition and the loop that closes it out.
Contractual Notice
The written notice a contract requires within a set window after an event. Often a condition precedent: miss the deadline and an otherwise valid claim can be forfeited.
Potential Change Order & Directive
The pipeline before a change order: a PCO is a priced proposal; a change directive orders the work before the price is agreed.
Punch List
The minor items left to finish or fix after substantial completion. The project reaches final completion only once the whole list is closed.
Request for Information (RFI)
The formal written question a contractor asks the design team when the contract documents are unclear, incomplete, or in conflict.
Submittals
Shop drawings, product data, and samples the contractor sends the design team to approve before fabrication. Tracked and aged on a submittal log.
Time Impact Analysis (TIA)
A prospective method that inserts a delay fragnet into the schedule update and reruns the critical path to measure how far a single event moved the completion date.
Scheduling
The critical path and everything that moves it: float, baselines, look-aheads, and schedule compression.
Baseline Schedule
The frozen, approved plan that progress is measured against. The data date divides actual from forecast; variance is the gap between the current update and the baseline.
Schedule Compression
Shortening the project without cutting scope: crashing adds resources (more cost), fast-tracking overlaps sequential work (more risk). Both act on the critical path.
Critical Path (CPM)
The longest chain of dependent activities, which sets the shortest project duration. Its activities have zero float, so delaying any one delays the whole job.
Total Float & Free Float
Total float is slack before the project finish slips; free float is slack before a successor slips. Zero total float means the activity is on the critical path.
Gantt Chart
The bar-chart view of a schedule: activities as bars, dependencies between them, the critical path highlighted. Built in P6 (XER) or MS Project (XML).
Look-Ahead Schedule
A short-interval (3- or 6-week) extract of the master schedule in crew-level detail, used to clear constraints before an activity is released to the weekly work plan.
Milestone
A zero-duration marker for a key event or deadline, such as substantial completion. Often tied to a payment or a contractual date, so a slipped milestone is also commercial.
Financial & Accounting
How a project books revenue and cost: percentage of completion, WIP, committed cost, and cash flow.
Unbilled Accruals
Estimated cost of work done or materials delivered that no vendor has invoiced yet, booked at month end so the period is not understated. Reverses when the real invoice lands.
Accounts Payable (AP)
Approved vendor and subcontractor invoices not yet paid, sitting inside Net 30 or Net 60 terms. A current liability, and part of incurred cost before any cash moves.
Bond & Surety
A three-party guarantee: the surety promises the owner that the contractor will perform and pay its subs. Bid, performance, and payment bonds, bought for a premium near 1% of contract.
Construction Cash Flow
The timing of money out and in. Costs leave as work is done; payment arrives later and minus retainage, routinely pushing a profitable job cash-negative until retainage releases.
Committed Cost
Money the project is obligated to spend but has not yet paid: signed subcontracts, issued POs, executed change orders. It reveals an overrun before the invoices arrive.
Current (Adjusted) Contract Value
The original contract sum plus executed change orders: the moving total that the schedule of values, pay-app percent complete, and earned revenue are measured against. Pending changes stay out until signed.
Direct vs Indirect Cost
Direct costs tie to a scope of permanent work; indirect costs run the jobsite with time. Direct scales with scope, indirect with the calendar, which is why delay attacks the indirect side first.
Construction Draw
A single payment released as work is completed, equal to the net amount due on the pay application. The draw schedule is the planned sequence of these releases across the job.
Earned Revenue
The revenue a contractor has earned by performing the work, cost percent complete times current contract value, whether or not it has been billed. Distinct from EVM earned value and from billings.
Cost to Complete
The forecast of money still required to finish the remaining work (ETC). Added to actual cost it gives the estimate at completion; a CPI-based forecast beats a straight-line guess.
General Conditions
The indirect, time-related costs of running a job: supervision, site office, temp utilities, safety. Because they accrue per day, a schedule delay hits them hardest.
Incurred Cost (Actual Cost / ACWP)
The value of work consumed to date whatever the cash timing: paid invoices plus accounts payable plus unbilled accruals. The actual cost that CPI, EAC, and cost-to-cost percent complete rely on.
Margin, Fee & Markup
The same profit read three ways: markup is a share of cost, margin a share of price, fee the agreed profit on a cost-plus or GMP job. An 11.1% markup is only a 10% margin.
Percentage-of-Completion Method
The accounting method that recognizes construction revenue as work is performed: cost to date ÷ total cost × contract. Distinct from EVM percent complete.
Revenue Recognition
When and how much contract revenue is recorded as earned. Percentage-of-completion (over time) vs completed-contract (at the end); under ASC 606, usually over time.
WIP Schedule
The monthly report reconciling contract, cost, percent complete, revenue earned, and billed, to show each job over- or underbilled. The CFO’s and surety’s core read.
Safety
The metrics and practices regulators and insurers watch: OSHA, EMR, TRIR, and leading indicators.
DART Rate
Days Away, Restricted, or Transferred: recordables with a day away or a work restriction times 200,000 divided by hours, sitting between TRIR and LTIR in scope.
Experience Modification Rate (EMR)
An insurer-set multiplier on workers-comp premium from a firm’s past claims versus peers. 1.0 is average; below 1.0 earns a credit; it often gates bidding.
Job Hazard Analysis (JHA/JSA)
Breaks a task into steps, names the hazard in each, and defines the control, done before the work so the crew agrees how every step is made safe.
Leading vs Lagging Indicators
Lagging indicators (TRIR, EMR) measure outcomes after they happen; leading ones (near-misses, observations, toolbox talks) measure the prevention that drives them.
Lost Time Incident Rate (LTIR)
Lost-time cases (days away from work) times 200,000 divided by hours, the severe subset of TRIR that counts only injuries that kept someone off work.
Near-Miss
An unplanned event that could have caused injury but did not. A leading indicator, since many near-misses precede each recordable, making reporting the earliest warning.
OSHA Recordkeeping
The agency that sets jobsite safety rules, and the injury recordkeeping (the 300 log, 300A summary, 301 form) whose counts drive every safety rate.
Personal Protective Equipment (PPE)
The last line of defense, hard hat to fall protection, worn when hazards cannot be engineered out. The lowest rung of the hierarchy of controls, measured by compliance.
OSHA Recordable Incident
A work-related injury or illness beyond first aid that must go on the OSHA 300 log. The foundational count behind TRIR, DART, and LTIR.
Stop-Work Authority
The documented right and duty of any worker to halt an unsafe task, without penalty, until the hazard is resolved, pushing the last safety decision to the person closest to the work.
Toolbox Talk & Pre-Task Plan
The short daily safety briefing before work: the toolbox talk covers a topic, the pre-task plan walks the day’s tasks, hazards, and controls. Both are leading indicators.
Total Recordable Incident Rate (TRIR)
The headline safety rate: recordable cases times 200,000 divided by hours worked, normalizing incidents to 100 full-time workers a year so any firm compares to any other.
Quality & Field
What the field produces and the inspectors check: daily reports, punch lists, rework, and completion.
As-Built Drawings
The drawings updated through construction to show what was actually built, every field change and deviation, handed over at closeout so the owner knows what is in the walls.
Commissioning
Systematically verifying that building systems are installed and perform as designed, through install checks, functional testing, and owner acceptance before handover.
Daily Construction Report
The dated record of a day on site, crew, work, equipment, weather, delays, and safety. The primary legal and management record a field team produces.
Field Report
Any structured report from the field, daily log, inspection note, observation, photo set, capturing what happened where the work is. The raw material of the project record.
Final Completion
When all work, including every punch item, is finished and accepted, closeout documents are delivered, and final payment and remaining retainage are released.
First-Pass Yield
The share of work that passes inspection the first time with no rework. A quality-efficiency measure: high yield means less rework, less schedule drag, lower cost of quality.
Construction Inspection
A formal check that completed work meets the drawings, specs, and code before it is covered or accepted. A pass advances the work; a fail triggers an NCR or punch item.
Rework
Redoing work that was not done right the first time. The most expensive and least visible cost on a project, consuming labor, material, and schedule while adding nothing.
Substantial Completion
The milestone when work is complete enough for the owner to occupy it, even with punch items left. It starts warranties, shifts risk, ends LDs, and releases most retainage.
Time & Materials (T&M) Ticket
The daily record of labor, equipment, and materials for work done on a time-and-materials basis. Signed in the field, it is the evidence behind a T&M change claim.
Roles & Parties
Who does what on a project: the GC, owner, CM, subcontractors, and the people who run the work.
Construction Manager (CM)
A firm engaged to manage the project for the owner, either as an agent (advising) or at-risk (holding the trade contracts under a guaranteed maximum price).
Estimator
The person who prices the work before it is built, building the estimate that becomes the budget and the bid, and the baseline every later cost reading is judged against.
Foreman
The frontline supervisor of a single crew or trade, directing the hands-on work and tracking the day’s production and headcount up to the superintendent.
General Contractor (GC)
The prime contractor who holds the owner’s contract and delivers the whole project, coordinating and paying the subcontractors who perform most of the trades.
Construction Lender
The bank or fund that finances a project, releasing money in draws against verified progress rather than all at once, with inspections before each release.
Owner (Project Owner)
The party who commissions and pays for the project and will own the finished asset, setting scope and budget and making the final calls on changes and acceptance.
Owner’s Representative
A professional who acts on the owner’s behalf to oversee scope, budget, schedule, and quality, protecting the owner’s interests without being the contractor.
Project Manager (Construction)
The person accountable for a project’s commercial and schedule outcome, budget, change orders, billing, and the plan, running the money while the super runs the field.
Subcontractor
A specialty trade contractor hired by the GC or CM to perform a defined scope under a subcontract. Most of the physical work on a project is performed by subs.
Superintendent
The person who runs the jobsite day to day, directing crews and subs, enforcing safety and quality, and producing the daily report. The field’s senior leader.
Construction Intelligence
The concepts behind a modern reporting platform: coverage, the morning brief, and field-to-dashboard intelligence.
Ask POD
POD’s built-in assistant: ask a question about your project in plain language and it answers from your uploaded reports, schedules, and pay apps, grounded in your data.
Coverage Score
A measure of how complete your project data is, the share of the fields POD tracks that your uploads populate, that climbs as you add records.
Field-to-Dashboard Reporting
The workflow where a field report, spoken, photographed, or typed on site, becomes a structured executive dashboard within minutes, with no manual re-keying.
POD Insights
The analysis in every POD report, notifications, warnings, and recommendations from specialized AI agents reading your project data, not just the numbers but what to do.
Construction Intelligence
Turning raw field data, reports, photos, schedules, pay apps, into structured, decision-ready insight, so a project is run from current fact rather than memory.
Construction Morning Brief
A daily digest POD generates each morning summarizing overnight changes, open risks, and the day’s priorities from your project data.
Daily Reporting Platform
Software that captures the daily construction report and turns it into a living project record and dashboards, replacing paper logs so the report becomes usable data.