Back online
Definitive Guide

Construction daily reportlegal requirements.

A 2026 reference for federal Davis-Bacon, state prevailing wage, and AIA contract record-keeping. The required content, the retention periods, and the mistakes that lose claims.

0.0
Federal Sources
0+
State Statutes
0.0
Year Max Retention
$0
Davis-Bacon Trigger $
Direct Answer

Construction daily report legal requirements come from three stacked sources: federal law (Davis-Bacon Act 29 CFR Part 5, Service Contract Act, FAR Part 22), state prevailing wage statutes (California Labor Code §1776, New York Labor Law §220, Illinois Prevailing Wage Act, and 10+ others), and contract forms (AIA A201-2017 §3.10, ConsensusDocs 200 §6.2.4). Most large projects trigger more than one source at once. The required content is the union of fields demanded by each applicable source. Retention periods range from 3 years (federal Davis-Bacon) to 10 years (statute of repose). When sources stack, the longest controlling period governs.

Required content by source

Each row is a field. Each column is a legal source. Build your daily report template to cover the union of required fields across all applicable sources on your project.

FieldFederalStateContract (AIA / ConsensusDocs)
Date and project IDRequired (29 CFR 5.5)Required (all states)Required (AIA A201 §3.10.3)
Weather and temperatureRecommended (force majeure)RecommendedRequired (AIA, ConsensusDocs)
Crew by name and classificationRequired (Davis-Bacon)Required (prevailing wage)Required (most owner contracts)
Hours worked per workerRequired (WH-347)Required (CA LC §1776, NY LL §220)Required (T&M, cost-plus contracts)
Prevailing wage rate paidRequired (Davis-Bacon)Required (public works only)Per contract terms
Work performed by locationRecommendedRecommendedRequired (AIA §3.10.3)
Equipment and hours of operationRecommendedRecommendedRequired (T&M billing)
Materials delivered and installedRecommendedRecommendedRequired (Schedule of Values support)
Subcontractors on siteRequired (flow-down)Required (public works)Required (AIA §3.10.3)
Visitors and inspectorsRecommendedRecommendedRequired (claims defense)
Delays and stoppagesRecommendedRecommendedRequired (excusable delay claims)
Accidents and safety issuesRequired (OSHA 29 CFR Part 1904)Required (state OSHA plans)Required (AIA §10)
Photographs of progressRecommendedRecommendedOften required (owner spec)
Test results and inspectionsPer specPer specRequired (AIA §13.5)

How to build a compliant daily report

Five steps from project intake to retention. Most projects trigger more than one source, so the workflow assumes the union case.

  1. 1

    Identify which requirements apply to the project

    Map funding source and contract form.

    Federal funding (HUD, FHWA, DOE, etc.) triggers Davis-Bacon and FAR Part 22. State or local public funding triggers state prevailing wage laws. Private projects under AIA A201-2017 or ConsensusDocs 200 trigger contract record-of-the-Work obligations. Most large projects trigger at least two requirements simultaneously, and the union of fields applies. A $24M school project funded partly by federal money under a CA Labor Code §1776 state contract executed on AIA A201 stacks all three.

  2. 2

    Assemble the required content matrix

    Build a template that captures the union of fields.

    Combine Davis-Bacon WH-347 fields (worker name, classification, hours, prevailing wage, deductions), state prevailing wage fields (apprentice ratios, fringe benefits where required), and AIA §3.10.3 record-of-the-Work fields (weather, work performed, equipment, materials, delays, visitors, photographs, test results). One template covers all requirements when assembled correctly.

  3. 3

    Capture contemporaneously with attribution

    Same day. Named individual. Timestamp.

    Federal courts and DOL Wage and Hour treat contemporaneous attribution as the legal floor. Each entry must be attributable to a named individual with a timestamp and be created on the day of the work. Voice capture, mobile app, or paper log are all acceptable formats. After-the-fact reconstruction is the most common cause of failed Davis-Bacon enforcement actions and the most common defense problem in claims litigation.

  4. 4

    File weekly certified payroll where required

    WH-347 federal. State forms for prevailing wage.

    For Davis-Bacon work, transfer daily labor data to Form WH-347 weekly and submit signed under penalty of perjury. For state prevailing wage work, follow the state-specific certified payroll form and submission cadence: CA uses the DIR online portal, NY uses Form PW-101, IL uses monthly LM-22, NJ uses biweekly forms. Missing filings trigger payment withholding and potential debarment.

  5. 5

    Retain for the longest controlling period

    Stack the retention rules. Apply the longest.

    Compare federal Davis-Bacon (3 years), state public works (4 to 7 years), IRS audit window (3 to 7 years), mechanics lien window (4 months to 2 years), and statute of repose (6 to 10 years). Apply the longest from project completion. For many large public projects the controlling period is 7 years. Retain daily reports, supporting timesheets, photographs, and weather data together in a single archive indexed by project and date.

Worked Example

A General Contractor is building a $24M public school in California. The project receives federal funding (HUD or DOE component), is bid as a California public works contract, and is executed on AIA A201-2017.

The requirements stack: Davis-Bacon (federal funding portion) plus California Labor Code §1776 (state prevailing wage) plus AIA A201 §3.10.3 (contract record-of-the-Work). The daily report template must capture certified payroll fields (worker, classification, hours, prevailing wage, deductions) plus state prevailing wage fields (apprentice ratios, fringe) plus contract progress fields (weather, work performed, equipment, materials, subs, visitors, photographs, test results).

Federal (Davis-Bacon)
3 years
29 CFR 5.5(a)(3)
CA Labor Code §1776
3 years
Statutory minimum
CA Statute of Repose
10 years
CCP §337.15 (latent defects)

The controlling retention period is 10 years from substantial completion, driven by California Code of Civil Procedure §337.15 (latent construction defect repose). Daily reports, supporting payroll, photographs, and weather data must all be retained for the full 10-year period.

State-by-state prevailing wage daily reporting

Ten states with active prevailing wage laws on public works projects. The retention column shows the state-specific minimum, not the longest applicable controlling period.

StateStatuteScopeRetention
CaliforniaLabor Code §1776Public works prevailing wage daily recordsAt least 3 years from completion
New YorkLabor Law §220Public works prevailing wage, daily reports6 years (NY general business)
TexasGovernment Code §2258Public works wage reports4 years post-completion
FloridaStatute §255.05Public construction payment and record requirements5 years post-completion
IllinoisPrevailing Wage Act (820 ILCS 130)Monthly certified payroll, daily underlying records5 years post-completion
MassachusettsM.G.L. c.149 §27Public works prevailing wage daily records3 years post-completion
New JerseyN.J.S.A. 34:11-56.25Public works contracts, daily certified payroll2 years (statutory minimum)
WashingtonRCW 39.12Public works prevailing wage daily records3 years post-completion
Pennsylvania43 P.S. §165 (PA Prevailing Wage Act)Public works weekly payroll, daily underlying records2 years (statutory minimum)
OhioO.R.C. §4115Prevailing wage daily records on public works2 years post-completion

Five compliance mistakes that lose claims

These show up in DOL enforcement actions, AIA delay disputes, and statute-of-repose defect cases. Each one is preventable with a contemporaneous, attributable daily report.

  1. 01

    Reconstructing reports days or weeks after the fact

    Federal courts and DOL Wage and Hour treat non-contemporaneous records as presumptively unreliable. The most common Davis-Bacon enforcement finding is "records reconstructed after notice of inspection." On AIA contracts, after-the-fact daily logs are routinely excluded from delay-claim evidence.

  2. 02

    Omitting weather data on schedule-sensitive projects

    Force majeure and excusable delay claims depend on contemporaneous weather records. AACE RP 25R-03 and most contract forms require start-of-shift, mid-shift, and end-of-shift entries with quantitative backing (temperature, precipitation, wind). A subjective "rained all day" entry will not support a delay claim.

  3. 03

    Treating subcontractor records as the sub problem

    On federal Davis-Bacon projects, the prime contractor is statutorily responsible for collecting and forwarding sub certified payroll (29 CFR 5.5(a)(3)). Failure to flow-down and collect is a prime-contractor violation regardless of which party omitted the record.

  4. 04

    Mixing up classification codes between trades

    Davis-Bacon and state prevailing wage rates are tied to specific labor classifications. Recording a Laborer doing pipefitter work at the Laborer rate is a wage violation even if the hours are accurate. The daily report must reflect the work performed, and pay must match the higher of the two applicable classifications for that work.

  5. 05

    Discarding records before the controlling retention period

    Multiple retention periods apply simultaneously: 3 years (Davis-Bacon), 4 to 7 years (state public works), 6 to 10 years (statute of repose). Companies routinely apply only the shortest period, then discover they have destroyed records needed for a defect claim or DOL audit years later.

Retention periods by source

When multiple sources apply, the longest controlling period governs. Calculate from substantial completion, not from the date of the entry.

Federal Davis-Bacon (construction)
3 years from completion
29 CFR 5.5(a)(3)
Federal Service Contract Act
3 years from completion
29 CFR 4.6(g)
IRS payroll and tax records
3 to 7 years
IRC §6501; IRS Pub 583
OSHA recordkeeping (300 log)
5 years from end of year
29 CFR 1904.33
State public works (typical)
4 to 7 years
Varies by state statute
Mechanics lien window
4 months to 2 years
Varies by state
Construction defect statute of repose
6 to 10 years
Varies by state
AIA A201 record retention (contract default)
Per contract; typically 6 years
AIA A201-2017 §13.4

Frequently asked questions

It depends on the project. Federal contracts under Davis-Bacon and the Service Contract Act require daily labor and payroll records (29 CFR Part 5). State public works under prevailing wage laws (CA Labor Code 1776, NY Labor Law 220, IL Prevailing Wage Act and others) require daily certified payroll. Private contracts typically require daily reports through AIA A201-2017 Section 3.10 or ConsensusDocs 200 Section 6.2.4. There is no universal federal rule that every construction project must keep a daily report, but most large projects fall under at least one of these requirements.

The Davis-Bacon Act (29 CFR Part 5) requires weekly submission of certified payroll on Form WH-347, signed under penalty of perjury. The underlying daily records must capture each worker by name, classification, hours worked per day, prevailing wage rate, gross wages, and deductions. The daily report obligation is the source data that supports the weekly WH-347 filing. Inaccurate daily entries are the most common cause of Davis-Bacon enforcement actions by the DOL Wage and Hour Division.

AIA A201-2017 Section 3.10 requires the Contractor to prepare and keep current Construction Schedules and, under Section 3.10.3, to keep an up-to-date record of the Work available to the Owner and Architect. Most owners interpret this as a daily report obligation covering crew, work performed, equipment, materials, weather, delays, and visitors. Failure to maintain these records is grounds for withholding payment under Section 9.5 and is a common defense problem in delay claims.

The required content varies by source but the union of common requirements covers: date, weather and temperature, crew composition by trade and classification, hours worked per worker, work performed by location and activity, equipment on site and operating hours, materials delivered and installed, subcontractors on site, visitors including inspectors, delays and accidents, safety observations, photographs of progress, and test or inspection results. Federal Davis-Bacon projects add prevailing wage fields. AIA contracts focus on schedule and progress. Both stack on public works projects.

Federal Davis-Bacon: 3 years post-completion per 29 CFR 5.5(a)(3). State public works: typically 4 to 7 years depending on the state. IRS audit window: 3 to 7 years. Mechanics lien window: varies from 4 months to 2 years by state. Construction defect statutes of repose: 6 to 10 years in most states. When multiple requirements apply, the longest controlling period governs, which for many public projects works out to 7 years minimum.

For Davis-Bacon and Service Contract Act work, the weekly WH-347 must be signed under penalty of perjury by an authorized officer or principal. The underlying daily records do not require a signature on each page, but they must be attributable to a specific person and dated. AIA and ConsensusDocs contracts do not mandate a signature on each daily report, but most owners require the superintendent or foreman to sign or electronically attribute the entry. Voice and digital attribution that includes user identity, timestamp, and device source are accepted by most owners and federal auditors.

Most contracts and AACE RP 25R-03 treat NOAA weather data as authoritative. For force majeure and weather-delay claims, the daily report must capture conditions at start of shift, mid-shift, and end of shift, along with the specific work activity that was prevented or impacted. Temperature high and low, precipitation totals, and wind speed are commonly required. A subjective entry like rained all day without quantitative backing is typically rejected in claims defense.

Yes, if the captured record meets the source requirement. Federal Davis-Bacon does not specify capture method, only content. AIA A201 Section 3.10.3 says record of the Work without prescribing format. State prevailing wage laws generally allow any format that preserves the required fields with attribution and timestamp. The legal test is whether the record is complete, attributable, contemporaneous, and tamper-evident. Modern voice-to-structured-record systems that timestamp, attribute, and lock entries pass this test on most projects.

On Davis-Bacon projects, missing weekly WH-347 filings can result in withholding of contract payments per 29 CFR 5.5(a)(2) and debarment from federal contracting for up to three years per 29 CFR 5.12. On state public works, penalties range from per-day fines (California Labor Code 1776(g): $100 per day) to contract suspension. Gaps in daily records also undermine delay claims, change-order pricing, and defect defense. The cost of one missed day frequently exceeds the cost of a year of daily reporting infrastructure.

On federal Davis-Bacon work, the prime contractor is responsible for collecting and forwarding subcontractor certified payroll per 29 CFR 5.5(a)(3). On AIA A201 projects, the General Contractor is responsible for the overall record of the Work but is not automatically liable for sub-level daily entries unless the contract specifies combined reporting. Best practice is to require sub daily reports as a flow-down provision in the subcontract and to retain them with the GC daily report file.

When POD is the natural answer

The hardest part of daily report compliance is not knowing the rules — it is capturing the union of fields contemporaneously, every day, across every crew, with attribution and a tamper-evident timestamp. Most projects fail not because the team did not understand Davis-Bacon, but because the foreman ran out of time at 6 PM and reconstructed three days of entries on Friday. Plan of Day is voice-first construction reporting that captures the required fields in the field, attributes each entry to a named user with a timestamp, routes prevailing wage data through POD's intelligence engine, and locks records into a tamper-evident archive that survives the longest controlling retention period. Specialized AI agents cross-check classification codes against work performed, flag missing weather entries on schedule-sensitive days, and assemble weekly WH-347 from daily source data without manual rekeying.

Sources

Last updated: May 2026