The measure ofprogress

Your cost report says half done.

Percent complete is not one number. A cost-based input reading and a physical output reading can sit almost nine points apart on the same job, and ASC 606 does not let you keep the convenient one. This guide is about choosing the measure: what each assumes, why uninstalled materials and rework are carved out of the input, and when only an output will do.

48.7%
Raw cost-to-cost
Why it matters

$19.0M spent of $39.0M estimated. Reads as nearly half done.

42.9%
Adjusted input
Why it matters

$4.0M of uninstalled equipment carved out of both sides of the ratio.

40%
Physical output
Why it matters

Surveyed work in place. The only reading that measures delivered work.

What a measure of progress is

A measure of progress is the method a contractor uses to decide how much of a performance obligation has been satisfied at a reporting date. ASC 606 recognizes revenue over time in proportion to that measure, so the choice between an input such as cost incurred and an output such as work in place sets the revenue figure itself.

The money-flow hub places progress inside the full circuit from incurred cost to the WIP position, and the percentage-of-completion guide runs the cost-to-cost arithmetic once the input measure is selected. Neither asks the question this page asks: which measure should the ratio be built on in the first place, and what has to be removed from it before it is honest.

The rules sit in a narrow band of the standard. ASC 606-10-25-31 sets the objective: depict the contractor’s performance in transferring control. ASC 606-10-25-32 requires a single method per performance obligation, applied consistently to similar obligations. ASC 606-10-25-36 permits over-time recognition only when progress can be reasonably measured. ASC 606-10-55-16 through 55-21 describe output methods, input methods, and the adjustments an input needs. The AICPA Revenue Recognition guide carries an engineering and construction chapter on the topic, and CICPAC, CFMA, and national CPA firms such as Baker Tilly have published implementation guidance on the uninstalled-materials question specifically, because it is where contractors most often get the input measure wrong.

Input and output methods, defined

An input method measures the effort consumed, almost always cost incurred against total estimated cost. An output method measures the work the customer has received: surveyed quantities, units installed, milestones certified. The first is cheap to run because the ledger already exists. The second is closer to the thing being measured. ASC 606 wants whichever one best depicts the transfer of control.

Set side by side on the $46.0M job this guide follows, where $39.0M of cost is expected, $19.0M has gone in, and $4.0M of that is switchgear and generators the owner holds title to in the laydown yard.

Input method (cost-to-cost)Output method (physical, units)
What it measuresEffort consumed: cost incurred, labor hours, machine hoursWork transferred: surveyed quantities, units installed, milestones certified
FormulaCost to date divided by total estimated costQuantity in place divided by total quantity in scope
What it assumesEach dollar of cost moved the job forward by the same amountThe survey or count is accurate and current
Where it distortsUninstalled materials, rework, front-loaded cost, and inefficiency all read as progressStale surveys; work in progress that sits outside the unit count
Data it needsThe job cost ledger and a current estimate at completionA quantity survey, inspector sign-off, or certified milestone each period
On the $46.0M job48.7% raw, 42.9% after the carve-out40% of the work in place
ASC 606 reference606-10-55-20 to 55-21606-10-55-17 to 55-18

The uninstalled-materials problem

Uninstalled materials are goods the customer controls before they are built in. Their cost sits in cost to date, so a raw cost-to-cost ratio counts them as progress. ASC 606-10-55-21 excludes that cost from the numerator and the denominator and recognizes revenue for the materials only to the extent of their cost, with zero margin.

On the $46.0M job, raw cost-to-cost is $19.0M over $39.0M, or 48.7 percent. Take the $4.0M of delivered equipment out of both sides and the ratio becomes $15.0M over $35.0M, or 42.9 percent. Applied to the $42.0M of transaction price that excludes the equipment, that is $18.0M of margin-bearing revenue. Add the $4.0M back at cost and recognized revenue is $22.0M. The raw reading would have booked $22.4M, which is $410K of margin recognized on equipment still on pallets.

The carve-out applies when, at contract inception, all four of the following hold:

  • The material is not a distinct performance obligation on its own
  • The customer takes control of it significantly before it is installed
  • Its cost is significant relative to total expected cost
  • You procured it from a third party and were not significantly involved in designing or making it
  1. 01
    Identify the uninstalled materials

    List materials delivered to the site or otherwise controlled by the customer but not yet installed, where the cost is significant, the item is not distinct, and you procured it rather than designed or manufactured it.

  2. 02
    Remove their cost from both sides of the ratio

    Subtract the uninstalled material cost from cost incurred to date and from total estimated cost before dividing.

  3. 03
    Compute the adjusted percent complete

    Divide the adjusted cost to date by the adjusted total estimated cost, then apply the result to the transaction price less the material cost.

  4. 04
    Recognize the materials at cost

    Add the material cost back as revenue equal to that cost, with zero margin, until the material is installed and absorbed into the measure.

The carve-out, drawn

One hatched slice is the $4.0M of equipment. Watch it drop out of the cost bar while the bar contracts behind it on both the spent side and the estimate side, and the reading falls from 48.7 to 42.9 percent. Then it travels down and docks on the end of the revenue bar, where it counts as revenue but carries no margin.

ASC 606-10-55-21Cost to date against estimated total cost48.7%$19.0M / $39.0MRevenue recognized against the $46.0M contract$4.0M uninstalledout of numerator and denominator$22.0M$18.0M carries margin, $4.0M at cost with zero marginThe raw read of 48.7% would have booked $22.4M.That is $410K of margin the work has not yet earned.

Rework and wasted cost are excluded

Cost that does not contribute to progress is left out of the measure. ASC 606-10-55-21(a) names unexpected amounts of wasted materials, labor, and other resources. The money is real and it stays in actual cost and in the estimate at completion, but it did not move the job forward, so it does not raise percent complete or release revenue.

Rework that corrects defects

Tearing out and re-pouring a slab doubles the cost of that slab and delivers it once. Under a raw input measure the second pour reads as progress. Under the standard it is excluded from the ratio, lowers margin through the estimate at completion, and leaves percent complete where the work actually is.

Expected inefficiency stays in

Normal waste factors, learning-curve hours, and weather allowances that were priced into the estimate are part of the cost of delivering the work. They remain in both sides of the ratio. The exclusion is for the unexpected and the non-contributing, not for every dollar that went badly.

Two edges deserve care. If the contract reimburses the wasted cost, as some cost-plus arrangements do, the cost may remain in the measure because the customer is paying for it. And front-loaded cost that did transfer control, such as engineering a customer-controlled design, is not waste and is not carved out; the test is whether control moved, not whether the spend was early.

When output is the better, or the only honest, measure

An output measure is required when cost incurred stops depicting the transfer of control and no adjustment repairs it. ASC 606-10-55-17 lists surveys of performance, appraisals of results, milestones reached, time elapsed, and units produced or delivered. The measure must be observable, and 55-18 permits an input only when the output cannot be seen without undue cost.

On the job in this guide the surveyed work in place reads 40 percent. Under a pure output measure the $4.0M of equipment is not progress at all until it is set and energized; it is simply inventory the owner happens to control. The 8.7-point gap between 48.7 and 40 is the distance between what was spent and what was built.

Unit-price and heavy civil

Cubic yards moved, linear feet of pipe, tons of asphalt. The pay item is the unit, the survey is the measure, and cost incurred is a poor proxy when a wet month doubles the hours per yard.

Repetitive production

Piles driven, panels set, turbines erected, rooms turned over. Units of delivery are observable, countable, and already tracked on the daily report.

Front-loaded procurement

Equipment-heavy jobs where generators, chillers, or transformers arrive long before they are set. An unadjusted input measure would recognize half the job before a crew touches it.

Owner-certified milestones

Where the contract pays on inspected stages, the certification is itself an output. Time elapsed alone is rarely acceptable because it depicts the calendar, not the work.

Two cautions come with output measures. ASC 606-10-55-17 warns that units produced or delivered do not faithfully depict performance when material work in progress or finished goods the customer controls sit outside the count at period end, so a units-of-delivery measure needs a work-in-progress adjustment of its own. And the choice is sticky: 606-10-25-32 applies one method consistently across the obligation and across similar contracts, so a contractor cannot read cost-to-cost in a good month and surveyed quantities in a bad one. Updating the inputs to a measure as the job moves is a change in accounting estimate under 606-10-25-35. Changing the measure itself is a change in accounting method.

In practice most building contractors keep the input method and discipline it with the carve-outs above, while heavy civil, utility, and renewables work leans on quantities. What the standard will not accept is the version where the measure is whichever one produces the number the quarter needs.

One job, three measures of progress

The same $46.0M job read three ways. The physical arm is the surveyed work in place at 40 percent. The earned arm carries the adjusted input reading, 42.9 rounded to 43, which is the value the cost ledger supports once the equipment is carved out. The schedule arm is the calendar: 47 percent of the planned duration has elapsed. The card’s verdict compares work in place to time elapsed, which is why it reads behind. The spread between the three is the information.

Progress Overview

0%
PhysicalWork Complete
0%
EarnedValue Complete
0%
ScheduleTime Elapsed
Behind schedule - action required
ReadingNumeratorDenominatorPercentWhat it books
Raw input$19.0M cost to date$39.0M estimated cost48.7%$22.4M, margin on equipment still on pallets
Adjusted input$15.0M, equipment out$35.0M, equipment out42.9%$22.0M, of which $4.0M at cost with zero margin
Physical outputSurveyed work in placeTotal scope40%Uninstalled equipment is not progress until it goes in

A stored cost file vs a read one

Choosing the measure is a judgment. Checking it is arithmetic on three inputs: what cost has gone in, what has been installed and billed, and what the field reports as complete. The judgment is only as good as how current those three are when the comparison is made.

Stored and reconciled by hand
  • ·Cost to date is exported from accounting after the period closes
  • ·Uninstalled materials are found by someone remembering what is in the yard
  • ·Quantities installed live on the pay application; percent complete lives on a weekly report; nobody has both open at once
  • ·The input and output readings are compared once a quarter, if at all
Read as the files arrive
  • ·POD reads the cost reports, pay applications, and progress reports a job already produces
  • ·Cost to date, quantities billed against the schedule of values, and reported percent complete stay current per project
  • ·The input reading and the output reading can be set side by side on this period’s numbers
  • ·The choice of measure, and the carve-outs, stay with your controller and CPA

POD does not select the measure of progress or apply the ASC 606 adjustments. It reads the cost, pay-application, and progress files a job already generates, keeping cost to date, billed quantities, and reported percent complete current per project, so when a controller asks whether the ledger and the field agree, the answer is about this period. It sits alongside the revenue recognition decision, the cost-to-cost mechanics, and the WIP schedule where the chosen measure meets the billings.

Measure of progress questions

What is the difference between the input method and the output method for percent complete?▾

An input method measures progress by the effort put in, almost always cost incurred as a share of total estimated cost. An output method measures the work the customer has actually received, such as surveyed quantities, units installed, or milestones certified. The input method is easy to run because the cost ledger already exists, but it presumes each dollar of cost converted into an equal measure of progress. The output method measures progress directly and is harder to observe between surveys. ASC 606-10-55-16 to 55-21 describe both and require whichever one best depicts the transfer of control.

Is cost-to-cost always allowed under ASC 606?▾

No. ASC 606-10-25-31 sets the objective, a measure that depicts the contractor’s performance in transferring control, 606-10-25-32 requires a single method applied consistently, and 606-10-25-36 lets revenue be recognized over time only when progress can be reasonably measured. Cost-to-cost is permitted when cost incurred tracks the work delivered, which is true for most labor-driven building work. It is not a free election: when cost arrives without a matching transfer of control, as with uninstalled materials or wasted effort, the standard requires an adjustment or a different measure.

How are uninstalled materials handled in percent complete?▾

Under ASC 606-10-55-21, when a contractor procures a material the customer takes control of well before it is installed, and that material is significant, not distinct, and not something the contractor designed or manufactured, its cost is excluded from both the numerator and the denominator of the cost-to-cost ratio. Revenue for that material is then recognized only to the extent of its cost, with zero margin. On the job in this guide, $4.0M of delivered but uninstalled equipment moves the reading from 48.7 percent to 42.9 percent and re-enters as $4.0M of revenue at cost.

Are rework and wasted costs included in percent complete?▾

No. ASC 606-10-55-21(a) says costs that do not contribute to progress, such as unexpected amounts of wasted materials, labor, or other resources, are excluded from the measure of progress unless the contract specifically reimburses them. Rework that corrects defective work falls here: the money is spent, it belongs in actual cost and in the estimate at completion, but it did not move the job forward, so it does not raise percent complete or pull revenue and margin forward.

When should a contractor use a physical or units-of-delivery measure?▾

Use an output measure when inputs and delivered work visibly diverge: unit-price and heavy-civil contracts with surveyed quantities, repetitive production such as piles driven or panels set, and jobs with large front-loaded material or equipment purchases. ASC 606-10-55-17 lists surveys of performance, appraisals, milestones reached, and units produced or delivered as acceptable outputs, and 55-17 warns that a units measure is not faithful if material work in progress controlled by the customer sits outside the count at period end. When the output cannot be observed without undue cost, the standard allows an input method instead.

How does POD relate to measuring progress?▾

POD does not choose the measure of progress or make the ASC 606 adjustments; that judgment stays with your controller and CPA. What it does is keep the inputs behind either measure current. It reads the cost reports, pay applications, and progress reports a job already produces and keeps cost to date, the quantities billed against the schedule of values, and the reported percent complete current per project, so the input and output readings can be compared on this period’s numbers rather than last month’s.

Compare the ledger to the field on this period’s numbers

POD keeps both readings current

Begin with the free budget tracker, then let POD keep the cost reports, pay applications, and progress reports your jobs already produce current, so cost to date and work in place can be compared the day the files land.