Back online
Definitive Guide

Schedule of Values.The document that bills the job.

A 2026 reference for the Schedule of Values in construction. How to build one, how to cost-load it for AIA G703, and how owners audit for front-loading.

0
Mobilization Cap (%)
0
Typical Line Items
0
Standard Retainage (%)
$0
Worked Example ($)
Direct Answer

A Schedule of Values is a line-item breakdown of the construction contract sum into measurable work items used for monthly progress billing. It is the required attachment to the AIA G703 Continuation Sheet that supports each AIA G702 Application for Payment. The sum of all SOV line items must equal the contract value for lump-sum work. The SOV is where owners audit for front-loading, where contractors plan cash flow, and where the entire monthly billing cycle gets translated from a single contract number into discrete pieces of work that get billed as they are completed.

Key terms at a glance

The Schedule of Values, the G703 form that carries it, the mobilization line that gets front-loaded, and the retainage column that decides cash flow. These four terms appear on every pay application.

SOV

AIA G702/G703 standard practice

Schedule of Values

Formula or rule
Sum of all line items = Contract Value
What it measures
Line-item breakdown of contract sum for billing
Healthy range
30-80 items ($1-10M); 100-500 items ($10M+)

G703

American Institute of Architects (AIA)

AIA Continuation Sheet

Formula or rule
Scheduled + Stored - Retainage = Net Due
What it measures
Monthly billing detail per SOV line item
Healthy range
Updated every pay period

Mob.

Industry norm; FAR Part 32 for federal

Mobilization Line Item

Formula or rule
% of Contract Value
What it measures
Pre-construction setup costs (bonds, site office, etc.)
Healthy range
1-5% of contract value; below 3% for federal

Ret.

Contract terms; state prompt-pay statutes

Retainage

Formula or rule
% withheld per pay period
What it measures
Owner-withheld portion of each payment
Healthy range
Typically 5-10% until substantial completion

How to build a Schedule of Values

Five steps that produce a defensible, audit-ready SOV. The same process applies whether the contract is $1 million or $100 million. Only the granularity changes.

  1. 1

    Mirror the cost code structure

    Organize the SOV by CSI MasterFormat divisions and project cost codes.

    Each major CSI division becomes a section header. Each work package becomes a line item. Tie every line back to a project cost code so the SOV is traceable from contract to billing to job-cost reporting. The same structure that drives your estimating system should drive your SOV. If the two diverge, billing and cost reporting will never reconcile.

  2. 2

    Set granularity to project size

    Target 30-80 line items for $1-10M projects; 100-500 for $10M+.

    Too few line items hide where the money is going and make front-loading easier to disguise. Too many line items create administrative burden every pay period without improving owner insight. Adjust to the contract type. Lump-sum projects need enough detail to support front-loading review. Cost-plus and GMP projects often need more granular line items because the SOV doubles as the cost-tracking framework.

  3. 3

    Separate general conditions, contingency, fee, and stored materials

    Break out the support costs that owners audit first.

    General conditions should be broken into its components: supervision, temporary utilities, project insurance, performance and payment bonds, dumpsters, temporary fencing, and project trailer. Contingency belongs on its own transparent line, not hidden inside other items. Contractor fee gets its own line. Materials stored on-site get separate line items distinct from installed work, with a separate column on G703 for stored-but-not-installed value.

  4. 4

    Cost-load each line item to sum to contract value

    For lump-sum, total must equal contract value exactly.

    Mobilization stays at or below 5 percent of contract value. Avoid pricing early-phase items above comparable later-phase items by the same trade. The same trade pouring foundation walls and pouring slab on grade should show similar unit rates unless scope justifies otherwise. Document any line that deviates from a normal unit rate so the owner has a paper trail during SOV approval. If the contract is cost-plus or GMP, the SOV is open-book and the total reflects the GMP ceiling.

  5. 5

    Format for AIA G703 and submit for approval

    Lay it out in G703 columns and get owner sign-off before the first pay app.

    The G703 Continuation Sheet has columns for item number, description, scheduled value, work completed previous, work completed this period, materials presently stored, total completed and stored, percent complete, balance to finish, and retainage. Submit the full SOV in this format for owner approval before the first pay application. Once approved, the SOV becomes the controlling billing document for the life of the project. Changes after approval require a change order or owner consent.

Worked example: $4.2M commercial office shell

A real-world SOV walkthrough: 42 line items across 9 CSI divisions, owner audit, and the negotiated outcome. The same pattern applies on any lump-sum project.

A general contractor submits the initial Schedule of Values for a $4.2 million commercial office shell. The SOV contains 42 line items organized into 9 CSI divisions. General Conditions total 6.8 percent of contract value. Mobilization is initially priced at $250,000, which is 6.0 percent of contract value. Sitework and foundation line items are priced about $120,000 higher than comparable unit rates from the estimating workbook would support. The total SOV sums to $4.2 million.

The owner audit identifies mobilization above the 5 percent industry norm and flags the unit-rate variance on sitework and foundation lines. The contractor agrees to re-price mobilization at 1.2 percent ($50,000) and to bring sitework and foundation unit rates in line with the estimating workbook. The reallocated $200,000 redistributes across mechanical, finishes, and the punch list line, which moves from 0.5 percent to 1.8 percent of contract value. Final approved SOV: $4.2 million total, mobilization at 1.2 percent, no front-loaded unit rates, punch list adequately funded.

Mobilization (Before)
6.0%
$250,000 of $4.2M
Mobilization (After)
1.2%
$50,000 of $4.2M
Reallocated
$200K
To MEP, finishes, punch list

SOV by contract type

The SOV looks different depending on the contract. Lump-sum SOVs are about front-loading detection. Cost-plus SOVs are about cost tracking. Unit-price SOVs combine the SOV with a rate schedule. T&M uses an SOV only for the fixed-fee portion.

AttributeLump SumCost-Plus / GMPUnit PriceT&M
SOV total must equalContract value exactlyGMP ceiling (open-book)Estimated total + unit scheduleFixed-fee portion only
Owner review focusFront-loading detectionCost tracking vs ceilingUnit rates + quantity assumptionsMarkup transparency
Cost-codingMirrors CSI MasterFormatMirrors job-cost codes 1:1Combined with unit-rate scheduleLess common; fee portion only
Front-loading riskHigh (mobilization, sitework)Low (open-book pricing)Moderate (unit balancing)Low (time-based billing)
Audit difficultyModerate (unit-rate variance)Low (open-book invoices)Moderate (quantity true-ups)Low (timesheet review)
Change order impactNew SOV line addedCost rolled into open-bookQuantity adjusted, unit rate heldHours adjusted at agreed rate
Typical granularity30-500 line items50-1,000+ line items20-150 unit categories5-20 fee lines

Five signals owners use to detect front-loading

Front-loading is the classic SOV audit finding. Owners look for these patterns during initial approval and on every pay application that follows.

  1. 01

    Mobilization above 5 percent of contract value

    Industry norm caps mobilization at 1-5 percent. Federal contracts often hold it to 2-3 percent. A mobilization line above 5 percent without a documented justification is the most common front-loading flag and the first item negotiated down during SOV approval.

  2. 02

    General Conditions disproportionate to project duration

    General conditions should scale with project duration and crew complexity. A 12-month project with general conditions at 12 percent of contract value warrants scrutiny if comparable projects ran 6-8 percent. Break general conditions into supervision, temp utilities, insurance, bonds, and trailers so each can be reviewed independently.

  3. 03

    Early-phase items over-valued relative to schedule weight

    Sitework, excavation, and foundation line items that consume 25 percent of contract value but only 15 percent of the schedule duration are the classic front-loading pattern. Owners cross-check the SOV against the resource-loaded schedule to catch this. The dollar weight of each line should track its physical weight in the schedule.

  4. 04

    Same trade with markedly different unit rates across line items

    A masonry contractor showing $18 per square foot for early-phase walls and $11 per square foot for later-phase walls is a front-loading signal unless scope variance justifies the gap. Audit unit rates by trade across the full SOV. Significant variance without documented scope difference is the strongest indicator of front-loading.

  5. 05

    Punch list line item missing or under-valued

    A missing punch list line or one valued below 1 percent of contract is a common signal. Contractors who front-load early-phase items often under-value the punch list line because they expect to absorb closeout costs into their fee. Owners hold retainage longer when the punch list line is suspiciously low.

Owner audit checklist for the SOV

Owner reps and project managers use checklists like this during SOV approval and again every pay period. Run your own SOV against it before submission.

Sum of all line items equals contract value exactly?
Required for lump-sum contracts. Any variance must be reconciled before approval.
Mobilization at or below 5 percent of contract value?
Industry norm. Federal contracts often hold to 2-3 percent. Above 5 percent requires written justification.
General Conditions broken into components?
Supervision, temporary utilities, insurance, bonds, trailers, dumpsters. Single lump-sum GC line is an audit red flag.
Contingency line transparent and reasonable?
Owner-controlled contingency typically 3-5 percent. Contractor contingency varies by contract type.
Retainage shown as a separate column on G703?
Required by AIA G703 format. Verify the retainage percentage matches the contract terms.
Stored materials on a separate line from installed work?
Stored materials require off-site insurance documentation and title transfer for billing.
Unit rates consistent across the same trade?
Significant variance without scope justification indicates front-loading. Audit by trade.
Punch list line item present and reasonably valued?
Typically 1-3 percent of contract value. Missing or below 1 percent is a closeout risk signal.

Industry benchmarks for SOV line items

Reference numbers used by owner reps, lenders, and federal cost engineers when reviewing a Schedule of Values. Sources include AGC, CFMA, FAR Part 32, and AACE International.

Typical SOV line item count ($1-10M project)
30-80
AGC of America SOV guidance
Typical SOV line item count ($10M+ project)
100-500
AGC of America SOV guidance
Industry norm mobilization (private work)
1-5%
Construction Financial Management Association practice
Federal contract mobilization cap
2-3%
FAR Part 32 progress payment practice
Standard retainage percentage
5-10%
AIA A201 and state prompt-pay statutes
Typical contingency line (owner-controlled)
3-5%
AACE International cost engineering guidance

Frequently asked questions

A Schedule of Values (SOV) is a line-item breakdown of the total contract sum into measurable work items used for progress billing. It is the required attachment to the AIA G703 Continuation Sheet that supports each AIA G702 Application for Payment. The SOV translates a lump-sum contract into the discrete units of work that get billed month over month as they are completed.

AIA G703 is the Continuation Sheet that itemizes the Schedule of Values for each Application for Payment. G702 is the cover sheet that summarizes the current pay request, certifications, and totals. G703 lists every SOV line item with scheduled value, work completed this period, work completed to date, stored materials, retainage, and balance to finish. The SOV is the data; G703 is the form that carries it month over month.

Industry practice ranges from 30 to 80 line items for a $1 million to $10 million project, and 100 to 500 line items for projects above $10 million. Fewer line items give owners poor visibility into where the money is going. More line items increase the administrative burden for both billing and review. The right number mirrors the project cost code structure, typically organized by CSI MasterFormat division.

Front-loading is the practice of inflating the scheduled value of early-phase line items so the contractor collects more cash earlier in the project. Common targets include mobilization, general conditions, sitework, and foundations. Front-loading is contractually permissible only within reason. Owners audit for it because it shifts payment risk from the contractor to the owner if the project is later abandoned or terminated.

Look for four signals: mobilization above 5 percent of contract value, general conditions disproportionate to project duration, early-phase trade line items priced markedly higher per unit than comparable later-phase items, and a missing or under-valued punch list line. Compare unit rates across similar line items by the same trade. Significant variance without scope justification is the strongest indicator.

A cost-loaded SOV assigns a dollar value to each line item and is used for monthly billing under AIA G702 and G703. A resource-loaded schedule assigns hours, crew sizes, or equipment quantities to each activity and is used for forecasting labor and equipment demand. The two are distinct documents. Best practice is to maintain both and keep them in sync so billing progress and physical progress tell the same story.

On lump-sum contracts, the SOV must sum to the contract value exactly and owners review primarily for front-loading. On cost-plus and Guaranteed Maximum Price (GMP) contracts, the SOV is open-book and used for cost tracking against the GMP ceiling. The line-item structure typically mirrors the cost code structure so actual costs roll up directly to SOV reporting. Unit-price contracts often combine the SOV with a separate unit-rate schedule.

Retainage is the portion of each progress payment withheld by the owner until the work is substantially complete, typically 5 to 10 percent. On AIA G703 it appears as a separate column for each line item and as a separate line on the G702 summary. Retainage is held against every SOV line item, not against the contract as a whole. The retainage column is the first place an owner audits when reviewing a pay application.

Yes. Federal contracts follow FAR Part 32 for progress payments, which includes specific SOV approval and cost-substantiation rules. The Federal Highway Administration (FHWA) publishes separate SOV requirements for federal-aid highway projects, organized by cost category. Department of Defense projects follow applicable MIL-STD requirements. Federal SOVs are reviewed more rigorously and front-loading limits are typically tighter than on private work.

Industry norm for mobilization is 1 to 5 percent of contract value. Owners commonly cap mobilization at 5 percent or require a written justification above that level. Federal contracts often cap mobilization at 2 to 3 percent. A mobilization line above 5 percent without a documented justification is the most common front-loading flag and is typically the first item negotiated down during the SOV approval phase.

When POD is the natural answer

The Schedule of Values lives in a spreadsheet. The G703 Continuation Sheet lives in a separate template. Daily field progress lives in a third place. Stored materials get tracked on a fourth. By the time pay day rolls around, somebody spends two days reconciling everything by hand. Plan of Day is voice-first construction reporting that captures daily progress from the field, ties each field observation back to its SOV line item, and feeds the cost-loaded SOV, stored materials log, and G703 worksheet in one place. POD's intelligence engine flags unit-rate variance and front-loading patterns before the pay application hits the owner's desk. The numbers reconcile because they came from the same source.

Sources

Last updated: May 2026