Solar PVConstructionon the Record
Utility-scale solar is measured in MWdc energized, not modules counted. POD gives the solar EPC a PV-specific daily report and dashboard — piles, tables, DC, inverters, and MWdc online — built from a voice note in the field.
"200 modules installed" is not a solar report
Your owner gets a line that says modules were installed — no rows completed per crew, no DC circuits landed, no inverters energized, no MWdc brought online. A generic construction template captures the count and misses the plant. Solar has to report the build the way it gets paid: by capacity online, block by block, the day it happens.
What a solar day has to carry
Irradiance & weather
The sun-hours the day actually delivered, and the wind or heat holds that stopped module lifts. Every production number reads against the resource.
Piles, racking & modules
Piles driven and refusals, tables built, modules set, torque-tube alignment. The physical build, block by block, not one lumped “modules installed” line.
DC & inverters
DC circuits pulled and landed, combiners energized, inverters and skids commissioned. The electrical scope that turns panels into power.
MWdc energized
The number the owner and the offtaker read first — direct-current capacity brought online, block by block, toward mechanical completion.
The whole array, from above
Panel rows set block by block, the sun sweeps the field, combiner boxes gather each block, and a medium-voltage line runs to the substation — a live map of a solar build.
What the solar build looks like on the dashboard
Two numbers a solar EPC reads first: is each scope installing on budget, and is the fleet working.
Cost Per Install Unit
Equipment Performance
The solar build POD tracks
From first pile to first megawatt — every phase reported the day it moves.
Civil & piles
Grading, access roads, and pile driving. Refusals and predrills are logged the day they happen — they drive the racking schedule.
Racking & modules
Tables assembled, modules set and clamped. Rows completed per crew per day is the productivity number that forecasts the finish.
DC & electrical
DC wire pulled, combiners and inverters set, MV collection run. The scope that connects the array to the substation.
Commissioning
String tests, inverter energization, and MWdc brought online. The punch that converts a built array into a producing plant.
Built for the solar build, not a generic form
| What gets tracked | Generic template | POD solar platform |
|---|---|---|
| Progress % | Plus rows set, blocks combined, MWdc energized | |
| Weather note | Sun-hours delivered + wind/heat holds on lifts | |
| Equipment | Pile drivers, telehandlers, tracker crews — worked vs waiting | |
| Install productivity | Cost per install unit by scope (piles, modules, DC, inverters) | |
| Electrical commissioning | DC circuits, combiners, inverters energized | |
| MWdc roll-up across blocks | One capacity number toward mechanical completion |
Free Solar PV template & KPI tools
Grab the free Solar PV daily-report template, or use POD's free KPI calculators — Google Sheets, Excel, or PDF. No account needed.
Solar construction questions
Yes. The solar day structures into the fields a solar owner actually reads — piles set, tables and modules installed, DC circuits pulled, inverters energized, and MWdc brought online — all from a field voice note or a few photos. The report shows the build the way the owner measures it, not a generic “200 modules installed” line.
Put the solar day on the record
Speak it from the field. POD builds the report, tracks the MWdc, and updates the dashboard before the crew leaves the site.