Construction Glossary · Change Management

Claims &Back Charges

When the normal change process breaks down, money moves two ways. A claim demands more from above; a back charge deducts from below. Both live or die on the record.

Definition

A construction claim is a formal demand for additional compensation or time beyond the contract, usually when a change could not be settled by change order. A back charge is a cost one party charges back to another, typically a general contractor deducting from a subcontractor for work or expenses the subcontractor should have borne, such as defective work, cleanup, or damage.

Which way the money flows

A general contractor sits in the middle. It makes a claim upward to the owner for cost or time it believes it is owed, and it issues a back charge downward to a subcontractor to recover costs the sub should have borne. Claims can run the other way too, an owner against a contractor, but the GC in the middle shows both directions at once.

OwnerGC / ContractorSubcontractorClaimmore cost or timeBack chargededuct costs

Two instruments, one requirement: the record

Claim

A formal demand for added cost or time the other side has not accepted, made under the contract's claims procedure when a change could not be settled by change order.

Won or lost on the contemporaneous record: daily reports, the RFI log, schedule analysis, and cost backup.

Back charge

A deduction for costs one party owes another, usually a GC recovering from a sub for defective work, cleanup, damage, or equipment the sub should have covered.

Defensible only with notice, an opportunity to cure, and documented actual costs tied to the specific failure.

How POD helps build the record

Claims and back charges are won on the contemporaneous record, and that record is what POD keeps as the project runs: dated daily reports, an RFI log with response times, the change-order history, and the cost picture, all captured day to day rather than reconstructed after a dispute. The record that defends a claim is the same one POD is building anyway, which is the quiet payoff of disciplined daily logging.

Delay analysis methodologies guide

Frequently asked questions

The record is the whole game

Claims and back charges both trace back to what the field recorded day by day. It starts with the RFI that never got answered and the change that never got signed.