The ChangeOrder
No project finishes as drawn. The change order is the written instrument that turns an informal "just add it" into an enforceable change to scope, price, and time.
A change order (CO) is a written amendment to a construction contract that modifies the scope of work, the contract price, the schedule, or some combination of the three. It is signed by the owner, contractor, and usually the architect, and once executed it becomes part of the contract, formally changing what was agreed.
From event to executed amendment
On our $12.0M project, a differing site condition adds $150K and five days. It travels four steps before it is real, and only the last one actually changes the contract.
Identify
An event changes the work: a differing site condition, an owner request, an RFI answer that adds scope. It is logged as a potential change order.
Price
The contractor prices the cost impact and the time impact, with backup, and submits a proposal for the change.
Negotiate
The owner and design team review the proposal, question the pricing, and the parties settle on a number and a time extension.
Execute
All parties sign. The change order becomes part of the contract, revising the contract sum and the completion date.
Change order vs directive vs PCO
Three instruments, three levels of agreement. Only the change order actually modifies the contract on signature.
| What it is | Signed before work? | Changes the contract? | |
|---|---|---|---|
| Change Order (CO) | Executed amendment to scope, price, time | Yes, by all parties | Yes, on signature |
| Change Directive (CCD) | Owner directs changed work before price is agreed | No, issued without contractor agreement | Not yet; converts to a CO later |
| Potential CO (PCO) | A logged, priced proposal for a possible change | No, it is a proposal | No, until approved as a CO |
The pipeline before a CO is covered in potential change orders & directives.
How POD tracks change orders
POD keeps an editable change-order log and reconciles it, separating changes to the client contract from changes to subcontracts. From there, each approved client change can be applied to the current project budget and the earned-value baseline, line by line, so the revised contract sum and the plan everything measures against move with the executed changes rather than drifting from them.
Change order management guideFrequently asked questions
Every change starts as a maybe
Before a change order is signed, it is a potential change order or a directive. That pipeline is where the money and the exposure live.