LiquidatedDamages
A number agreed at signing, charged for every late day at the end. Liquidated damages turn the finish date into a meter that runs against the contractor.
Liquidated damages (LDs) are a fixed sum, set in the contract as a daily rate, that the contractor owes the owner for each day the project finishes late when the delay is non-excusable. They are a pre-agreed estimate of the owner's actual loss from late completion, fixed at signing because that loss is hard to prove later. To be enforceable they must be a genuine pre-estimate, not a punitive penalty.
The meter starts at the adjusted finish date
On our $12.0M project the contract sets LDs at $5,000 per day. Twenty non-excusable days late is a $100,000 charge. Every granted time extension slides the Day-0 line to the right and erases the days behind it.
Why a penalty is unenforceable
A liquidated-damages rate survives only if it looks like a forecast of real loss. The moment it looks like a threat, courts tend to strike it.
| Liquidated damages | Penalty | |
|---|---|---|
| Purpose | Pre-estimate the owner’s actual loss | Punish or coerce performance |
| Set when | At contract signing, from probable harm | Arbitrary, unrelated to likely harm |
| Enforceable? | Usually yes, if reasonable | Usually no |
| Owner must prove actual loss? | No — the rate stands in for it | N/A — the clause fails |
How POD helps defend the exposure
Liquidated-damages exposure is really a completion-date argument, and that is where POD helps. POD reads the project schedule from a Primavera P6 or MS Project import, including the substantial-completion milestone, while its excusable-events and notice records build the case for every time extension that moves the adjusted finish date. POD does not set your liquidated-damages rate or calculate the owner's claim; it keeps the schedule and the entitlement record that decide how many late days are actually exposed.
Delay analysis methodologies guideFrequently asked questions
The best defense is a moved finish line
Every excusable day proven is a day of liquidated damages erased. That proof is a delay analysis built on contemporaneous records.