Construction Glossary · Change Management

ForceMajeure

The hurricane nobody could stop still has to be handled by the contract. Force majeure decides who absorbs the lost time, and who absorbs the lost money.

Definition

Force majeure is a contract clause, and the class of events it names, covering extraordinary occurrences beyond either party's reasonable control, such as hurricanes, floods, earthquakes, war, or government action, that prevent performance. As a delay, a force majeure event is usually excusable but non-compensable: the contractor earns a time extension, but no money, and the owner cannot assess liquidated damages for that period.

What the event moves, and what it does not

A named-storm shutdown stalls the critical path on our $12.0M project for twenty working days. The finish date moves out; the contract price does not.

Planned finish+20dForce majeure
Time extension granted No compensation LDs blocked

What usually counts, and what usually does not

The clause lists specific events and then adds a catch-all. The line is drawn at genuine impossibility beyond either party's control, not mere difficulty or expense.

EventTypically force majeure?Why
Hurricane, flood, earthquakeYesClassic acts of nature beyond control
War, civil unrest, government orderYesSovereign or societal, not contractor-driven
Unusually severe weatherOftenOnly if it exceeds the normal expected for the season and locale
Normal rain, routine labor shortageNoForeseeable and part of ordinary performance risk
Contractor’s subcontractor defaultNoWithin the contractor’s sphere of responsibility

How POD documents the event

POD logs the force majeure event in its excusable-events register and pairs it with the field record that substantiates it: the dated daily reports showing work stopped, and POD's weather intelligence, which tracks the forecast and reasons about its impact on the schedule. Because the evidence is captured the day it happens rather than rebuilt from memory, the notice and the mitigation story hold up later. POD does not decide whether an event qualifies under your clause; it keeps the contemporaneous proof the determination depends on.

Delay analysis methodologies guide

Frequently asked questions

An act of God still needs a paper trail

Force majeure excuses the delay, not the notice. The clause only protects a contractor who claims it on time and proves the impact.