Back online
Construction cost data

Construction cost overruns: the data.

Nine out of ten large projects run over budget. Here is how common overruns are, how large they get, why they happen, and the numbers you can cite, with the calculators to price your own risk.

Cost overruns are closer to the rule than the exception in large construction. In Bent Flyvbjerg's study of 258 transport-infrastructure projects, roughly 90 percent ran over budget. McKinsey reports that large projects across asset classes typically run up to 80 percent over budget and about 20 percent longer than planned. The causes are consistent, and so are the defenses.

How large the overruns get

Flyvbjerg, Holm and Buhl studied 258 transport-infrastructure projects across 20 nations. Average cost escalation by project type:

Project typeAverage cost overrun
Rail44.7%
Bridges & tunnels33.8%
Roads20.4%

Source: Flyvbjerg, Holm & Buhl, "Underestimating Costs in Public Works Projects: Error or Lie?" (JAPA, 2002); "How common and how large are cost overruns in transport infrastructure projects?" (Transport Reviews, 2003). ~9 in 10 projects overran.

Megaprojects are worse

FindingFigure
Typical cost overrun, large projectsup to 80%
Typical schedule slip~20% longer
Megaprojects over budget by >30%98%
Megaprojects at least 40% late77%

Source: McKinsey Global Institute, "Reinventing Construction: A Route to Higher Productivity" (February 2017).

Why projects run over

Optimism bias

An honest tendency to underestimate cost and duration and to assume the best case. It is the most common driver in the research.

Strategic misrepresentation

Costs understated to get a project approved. Once approved, scope growth, site unknowns, and escalation compound an already-thin estimate.

Price your own overrun risk

Questions & answers

Very. In Bent Flyvbjerg’s study of 258 large transport-infrastructure projects worldwide, roughly nine out of ten ran over budget. McKinsey’s Global Institute reports that large projects across asset classes typically run up to 80 percent over budget and take about 20 percent longer than scheduled. Overrun is closer to the rule than the exception.

Sources

  • Flyvbjerg, Holm & Buhl (2002), "Underestimating Costs in Public Works Projects: Error or Lie?" Journal of the American Planning Association.
  • Flyvbjerg, Holm & Buhl (2003), "How common and how large are cost overruns in transport infrastructure projects?" Transport Reviews.
  • McKinsey Global Institute (February 2017), "Reinventing Construction: A Route to Higher Productivity." mckinsey.com
  • AACE International Recommended Practices 40R-08, 44R-08, 17R-97, 18R-97 (contingency & estimate classification).

Catch the overrun while there is still budget.

POD reads the cost and change data your team already records and keeps an overrun-risk view current across the whole job, so the warning arrives early, not at closeout.

Last updated: July 2026