Back online
Free · AIA G702/G703 format · No email required

Construction Pay Application Template

Free AIA G702/G703 format pay application template. Contract sum, change orders, schedule of values, retainage, and current payment due — all calculated. Ungated, printable, Google Sheets-compatible.

0
G702 Summary Lines
0
G703 Columns
0
Line Items (Expandable)
0
Email Required

What a Complete Pay Application Should Include

A complete AIA G702/G703 pay application has twelve structural components. Missing any one of them is grounds for the owner or architect to reject the pay app and restart the 30 to 90-day payment clock.

This template covers all twelve. Every line and column below maps to a specific location in the HTML.

1. Application Header

13 fields

Application number, billing period, project name and number, contract date, project address, owner, contractor, and architect. The header travels with the document forever — auditors and lenders look at it first.

2. Original Contract Sum

Line 1

The signed contract amount before any change orders. This is the anchor for every downstream calculation on the pay app — get it from the signed contract, not from memory.

3. Change Orders

Line 2 + grid

Net of all approved change orders as of this billing period (additions minus deductions). Pending, requested, and in-flight COs do not belong here — only approved and signed. Supported by a detailed CO grid.

4. Contract Sum to Date

Line 3

Line 1 + Line 2. The adjusted contract total that the G703 schedule of values must sum to. If Line 3 does not match the Column C total in the schedule of values, the pay app will be rejected.

5. Schedule of Values (G703)

20 line items · 10 cols

One row per division of work — scheduled value, previous applications, this period, stored materials, total to date, percent complete, balance to finish, and retainage. 20 common line items pre-filled (expandable).

6. Work Completed This Period

Column E

Per line item, the dollar value of work completed between the period-from and period-to dates. Must be defensible against actual site progress — owners challenge inflated percent complete more than any other number.

7. Materials Presently Stored

Column F

Materials invoiced but not yet installed. Usually requires a bill of sale and proof of insurance on the stored materials. Separated from completed work because many contracts retain at a different percentage on stored materials.

8. Total Completed & Stored

Column G · Line 4

Column G = D + E + F for each line item. The G703 Column G total flows into G702 Line 4 as Total Completed and Stored to Date. This number anchors the entire payment calculation downstream.

9. Retainage Calculation

Lines 5a, 5b, 5

Split into retainage on completed work (5a — typically 5-10% of D+E) and retainage on stored materials (5b — often at a different percentage). Total retainage on Line 5. Line 6 is total earned less retainage.

10. Previous Certificates for Payment

Line 7

Sum of all money already paid on prior certificates. Net of any returned payments or deductions. Must reconcile with the owner's payment ledger — mismatches here are the most common cause of a 90-day payment dispute.

11. Current Payment Due

Line 8

Line 6 minus Line 7. The amount the owner owes for this billing period. Usually due 30 days after certification under AIA terms — statutory prompt-payment acts set the enforceable deadline (typically 60-90 days).

12. Signatures

Contractor · A/E · Owner

Contractor certifies the amount. Architect or engineer certifies the reviewed amount. Owner approves the amount paid. Three signatures, three certified totals. Without signatures, the pay app is a draft — not a billable document.

How This Template Compares

Most pay application templates and platforms handle the basic G702 arithmetic but skip the pieces that matter on real projects — retainage split, change order integration, and lien waiver tracking. Here is how Plan of Day compares.

AIA G702/G703 format
Sometimes — many vendors use generic invoice layouts
Yes — exact G702/G703 structure with all 9 summary lines and 10 schedule-of-values columns
Auto-calculated totals
Manual — contractor computes every number
All calculated from line-item data in the AI platform
Retainage split (completed vs stored)
No — single retainage line is typical
Yes — 5a (completed) and 5b (stored materials) tracked separately
Schedule of Values line items
Limited rows, no line-item history
Unlimited line items with full billing history per item
% Complete per line item
Yes — static
Yes — animated and cross-checked against daily progress data
Change Order integration
Separate document, manual reconciliation
Integrated — approved COs auto-feed Line 2 and flow into the G703
Lien waiver tracking
No — waivers managed outside the pay app
Yes — conditional and unconditional waivers tracked against every pay app in the platform
Email required to download
Yes (most vendors gate the download)
No — ungated, direct download
Price
Free (template) / several thousand dollars per user per year (platforms, per publicly available pricing)
Free template · Plan of Day platform $33-624/mo

Feature comparisons based on publicly available information from each vendor as of April 2026.

How to Fill Out an AIA G702/G703 Pay Application

Five steps. Thirty minutes total if your source data (contract sum, approved COs, subcontractor pay apps) is clean. Do it the same way every period and your pay applications will move through architect review and owner approval without rejection rounds.

1
3 min

Enter the application header

Fill in the application number (sequential — 001, 002, 003), billing period from and to, application date, project name and number, contract number and date, project address, owner name, contractor name, and architect or engineer of record. The header is boilerplate-feeling data that becomes evidentiary the moment a pay app is pulled into a dispute. Use the same project name and number on every pay app for the life of the project — inconsistent names across twelve pay apps is the first thing a forensic accountant flags during an audit.

2
5 min

Pull contract sum and change orders (Lines 1-3)

On Line 1, enter the original contract sum from the signed contract — the number before any change orders. On Line 2, enter the net of all approved change orders as of this billing period (additions minus deductions). Document each approved CO in the Change Order Summary grid. Line 3 (contract sum to date) is Line 1 plus Line 2, and it must equal the Column C total on your G703. Pending change orders, change order requests (CORs), and potential change orders (PCOs) do NOT belong on Line 2 — only approved and signed COs. This is the single most common source of pay-app rejection: owners reject pay apps where the contractor baked in pending COs.

3
12 min

Fill the G703 Schedule of Values

For each line item (division of work), enter scheduled value (Column C — must sum to Line 3), work from previous applications (Column D), work this period (Column E), materials presently stored (Column F), total completed and stored (Column G = D + E + F), percent complete (Column H = G ÷ C), balance to finish (Column I = C − G), and retainage (Column J). The Column G total flows into G702 Line 4 as Total Completed and Stored to Date. Every percent complete you enter should be defensible against actual progress on the ground. A line item at 60 percent complete on the pay app with a foreman reporting 40 percent in the daily log is a lawsuit waiting to happen. Cross-check before you submit.

4
5 min

Calculate retainage (Lines 5a, 5b, 5, 6)

Most construction contracts specify retainage as 5 to 10 percent of completed work, with a separate (often lower) percentage on stored materials. On Line 5a, enter retainage on completed work (percent × G703 Columns D+E total). On Line 5b, enter retainage on stored materials (percent × Column F total). Line 5 is the sum of 5a and 5b. Line 6 is total earned less retainage (Line 4 − Line 5). If your contract includes retainage reduction at substantial completion, or release at punch-list sign-off, state the adjustment explicitly in the Notes section and document the milestone. Public works in many states cap retainage by statute at 5 percent — check your jurisdiction before holding more.

5
5 min

Calculate current payment due and sign

Line 7 is the sum of all previous certificates for payment — every dollar already received through prior pay apps, net of any returned payments. Line 8 is the current payment due (Line 6 − Line 7). Line 9 is the balance to finish including retainage (Line 3 − Line 6). Attach the current-period conditional waiver and the prior-period unconditional waiver from the contractor, and the same from every tier-one subcontractor. Sign as Contractor. Send to the architect or engineer, who certifies the Certified Amount after review. Owner signs Approved Amount when approving payment. Three signatures; pay app is done. Under statutory prompt-payment acts, payment is typically due 30-90 days after certification depending on state.

Why Pay App Accuracy Compounds

A rejected pay app restarts the payment clock, compresses cash flow, and damages the owner-contractor relationship. The numbers below are why reconciled pay apps — not pretty pay apps — win repeat work.

90 days

Statutory prompt-payment deadline in most U.S. states once the pay app is certified

Source: State prompt-payment acts (AGC summary)

5-10%

Typical retainage held on construction pay applications (varies by contract and jurisdiction)

Source: AGC contract practice data

$177B

Annual U.S. cost of poor project data in construction, including billing and reconciliation errors

Source: FMI / Autodesk, 2021

~47 days

Average days sales outstanding on commercial construction projects

Source: CFMA industry benchmark data

~3%

Average change-order value as a percent of original contract on typical commercial projects

Source: Dodge Data & Analytics

700+

Daily decisions on a construction jobsite that should be captured and tied back to pay apps

Source: Plan of Day field research

This Template Takes 3 Hours. Plan of Day Takes 5 Minutes.

A free template gets you to G702/G703 format. Plan of Day closes the loop — percent complete from daily field data, COs auto-reconciled, lien waivers tracked, payment forecast.

The Template Way

Manual — 2-4 hours per pay app

Chase every subcontractor for their pay apps and lien waivers
Reconcile approved change orders against pending COs manually
Estimate line-item percent complete (no tie to actual daily progress)
Recompute retainage on completed work and stored materials by hand
Transcribe G703 totals into G702 Line 4 and pray the math checks out
Deal with architect rejection rounds over percent complete disputes

The Plan of Day Way

AI-powered — 5 minutes per pay app

Auto-generates G702/G703 from daily progress data already in the platform
Auto-reconciles approved change orders into Line 2 and the G703
Line-item percent complete pulled directly from the daily log
Retainage (completed + stored) calculated per contract terms
Lien waivers tracked and matched to every pay app automatically
Cash-flow gaps flagged before they hit the project

Frequently Asked Questions

An AIA G702/G703 pay application (also called an application for payment, progress billing, or draw request) is the industry-standard two-part document a contractor submits to an owner or architect to request payment for work completed during a billing period. G702 is the one-page summary — original contract sum, change orders, total completed to date, retainage, previous payments, and current amount due. G703 is the continuation sheet — a line-by-line schedule of values showing scheduled value, work previously completed, work this period, materials stored, total to date, percent complete, and balance to finish for every division of work. Owners, architects, and lenders rely on the G702/G703 format because it forces the contractor to show their math — you cannot hide progress claims or retainage calculations inside a narrative invoice.

The G702 is a nine-line summary at the project level. Line 1 is the original contract sum. Line 2 is the net change by approved change orders. Line 3 is the contract sum to date (1 + 2). Line 4 is total completed and stored to date, pulled from G703 Column G. Line 5 is total retainage (split into 5a on completed work and 5b on stored materials). Line 6 is total earned less retainage (4 − 5). Line 7 is the sum of all previous certificates for payment. Line 8 is the current payment due (6 − 7). Line 9 is the balance to finish including retainage (3 − 6). The G703 is a line-item schedule with ten columns — item number, description of work, scheduled value, work from previous applications, work this period, materials presently stored, total completed and stored to date, percent complete, balance to finish, and retainage. Totals from G703 flow up into G702 Line 4.

Yes, completely free. No email required, no account, no trial period, no watermark. Download the editable HTML file, fill out the G702 summary and G703 schedule of values in your browser, and print to PDF or save offline. The template mirrors the AIA G702/G703 layout but is not an AIA document and is not endorsed by the American Institute of Architects. It is suitable for internal use, subcontractor-to-GC billing, and owner-billed projects that do not mandate AIA-branded forms. If your contract requires the official AIA form, use this template as your working draft and transcribe the final numbers into the AIA document.

Retainage (or retention) is a portion of each pay application held back by the owner until the project is substantially complete, as insurance that the contractor will finish the work and correct any defects. Typical retainage on U.S. commercial construction is 5 to 10 percent of completed work, often reduced or released after a milestone (substantial completion, punch list complete) under terms negotiated in the contract. Some states cap retainage by statute on public works (commonly 5 percent). The G702 splits retainage into two lines: 5a on completed work and 5b on stored materials — because some owners reduce retainage on stored materials once a bill of sale is provided. Your contract governs the exact percentage, the milestone for release, and whether stored materials are treated separately.

For a single project or a small portfolio, yes. This free template covers the entire G702/G703 format — application header, contract sum, change orders, schedule of values, retainage split, previous certificates, current payment due, and signatures. What the template does not do is auto-reconcile change orders, auto-generate line-item percent complete from daily progress data, track lien waivers against pay apps, or forecast cash-flow gaps across a portfolio. Platforms typically priced at several thousand dollars per user per year per publicly available pricing do those workflows, and Plan of Day does them at a small fraction of that. The template is the right tool if you want G702/G703 today without signing up for anything; Plan of Day is the right tool when you want the reconciliation, forecasting, and lien-waiver tracking automated.

Lien waivers are the documents that protect the owner from mechanics liens filed by subcontractors or suppliers after payment. On most projects the contractor must submit conditional waivers with the pay application (effective on payment) and unconditional waivers the following period (acknowledging prior payment received). Subcontractor waivers typically track the same cadence. The template includes a Supporting Documentation section with checkboxes for conditional, unconditional, subcontractor, and stored-material waivers — but the waivers themselves are separate documents attached to the pay app. Best practice: never release payment without the current-period conditional waiver, and never accept a pay app in the next period without the prior-period unconditional waiver. Plan of Day tracks these waivers automatically against each pay app and flags missing or stale waivers before the GC submits.

Yes. Approved change orders adjust the contract sum and therefore the pay application. On the G702, the net of all approved change orders (additions minus deductions) goes on Line 2, and Line 3 (contract sum to date) reflects the adjusted total. Each approved change order should also appear as its own line item on the G703 Schedule of Values with its own scheduled value, or be reflected as an adjustment to an existing line item — whichever your owner or architect prefers. Pending change orders (PCOs), requests for change (RFCs), and change order requests (CORs) are NOT included in Line 2 until approved. The template includes a Change Order Summary section that feeds Line 2, so you can document the approved CO pool that supports your contract sum adjustment. Keeping pending and approved change orders straight is one of the most common sources of pay app disputes.

A typical monthly pay application on a mid-size commercial project takes 2 to 4 hours to prepare manually: gathering subcontractor pay apps, reconciling change orders, calculating percent complete per line item, computing retainage, checking lien waivers, and assembling supporting documentation. Large projects with 50+ line items and many subcontractors can take a full day. The bottleneck is not the G702 itself — that is just arithmetic. The bottleneck is reconciling percent complete with actual progress on the ground, matching subcontractor waivers to their pay apps, and confirming which change orders are approved this period. Plan of Day eliminates the bottleneck by pulling percent complete from daily progress data already captured in the field, auto-matching lien waivers to pay apps, and tracking change-order approval status in real time — the pay app generates itself at the end of the billing period with the numbers already reconciled.

Download the Free Pay Application Template

No email. No account. AIA G702/G703 format, ready to fill out in your browser.

Last updated: April 2026