Back online
Construction Glossary · Billing & Pay Apps

AIA G702 & G703Pay Applications

The two forms behind nearly every commercial progress payment: a one-page summary that gets certified, and the line-by-line sheet that proves it.

Definition

A pay application is a contractor's formal request for progress payment. On most commercial projects it uses two AIA forms: the G702 Application and Certificate for Payment, a one-page summary of the amount earned and due, and the G703 Continuation Sheet, the line-by-line breakdown from the schedule of values that supports it.

How the two forms reconcile

The G703 lines add up to the summary on the G702. On our $12.0M project, Application 8 shows $5.7M completed and stored, and after retainage and prior payments, $0.63M is due this period.

G703 — Continuation Sheet
General conditions$0.7M
Sitework$1.6M
Concrete/structure$1.9M
Steel/masonry$0.6M
Finishes$0.1M
MEP$0.5M
GC fee/overhead$0.3M
Completed & stored$5.7M
G702 — Application & Certificate
Total completed & stored to date$5.7M
Less retainage (10%)($0.57M)
Total earned less retainage$5.13M
Less previous certificates($4.50M)
Current payment due$0.63M

What the G702 summarizes

Every application carries the same core fields, each flowing from the contract and the continuation sheet.

FieldWhat it isOur example
Original contract sumThe starting contract value$12.0M
Change orders to dateNet approved changes$0.0M
Contract sum to dateContract plus changes$12.0M
Completed & stored to dateFrom the G703 line totals$5.7M
RetainageWithheld, usually 5-10%$0.57M
Total earned less retainageCompleted and stored, minus retainage$5.13M
Less previous certificatesWhat was already paid$4.50M
Current payment dueThe check this period$0.63M
Balance to finishContract sum less total earned less retainage$6.87M

Apply, certify, pay

Step 1

Contractor applies

The contractor fills the G703 from the schedule of values, rolls it into the G702, and signs the application certifying the work is done.

Step 2

Architect certifies

The design team reviews against the work in place and certifies the amount, in full or reduced. Only certified amounts get paid.

Step 3

Owner pays

The owner pays against the certificate, less retainage. That payment becomes the "previous certificates" line on the next application.

How POD reads a pay application

POD reads AIA G702 and G703 pay applications and reconciles the continuation-sheet lines against the summary so the figures tie out. The completed-and-stored total flows into POD's earned-value engine, and the retainage and amount-due math is tracked per line, so a billing picture that used to live in a stack of forms becomes queryable project data.

Construction billing methods guide

Frequently asked questions

The form is only the surface

Behind every pay app is the schedule of values that drives it and the retainage that holds part of it back. Start with the document that defines the lines.

Last updated: October 2026