AIA G702 & G703Pay Applications
The two forms behind nearly every commercial progress payment: a one-page summary that gets certified, and the line-by-line sheet that proves it.
A pay application is a contractor's formal request for progress payment. On most commercial projects it uses two AIA forms: the G702 Application and Certificate for Payment, a one-page summary of the amount earned and due, and the G703 Continuation Sheet, the line-by-line breakdown from the schedule of values that supports it.
How the two forms reconcile
The G703 lines add up to the summary on the G702. On our $12.0M project, Application 8 shows $5.7M completed and stored, and after retainage and prior payments, $0.63M is due this period.
What the G702 summarizes
Every application carries the same core fields, each flowing from the contract and the continuation sheet.
| Field | What it is | Our example |
|---|---|---|
| Original contract sum | The starting contract value | $12.0M |
| Change orders to date | Net approved changes | $0.0M |
| Contract sum to date | Contract plus changes | $12.0M |
| Completed & stored to date | From the G703 line totals | $5.7M |
| Retainage | Withheld, usually 5-10% | $0.57M |
| Total earned less retainage | Completed and stored, minus retainage | $5.13M |
| Less previous certificates | What was already paid | $4.50M |
| Current payment due | The check this period | $0.63M |
| Balance to finish | Contract sum less total earned less retainage | $6.87M |
Apply, certify, pay
Contractor applies
The contractor fills the G703 from the schedule of values, rolls it into the G702, and signs the application certifying the work is done.
Architect certifies
The design team reviews against the work in place and certifies the amount, in full or reduced. Only certified amounts get paid.
Owner pays
The owner pays against the certificate, less retainage. That payment becomes the "previous certificates" line on the next application.
How POD reads a pay application
POD reads AIA G702 and G703 pay applications and reconciles the continuation-sheet lines against the summary so the figures tie out. The completed-and-stored total flows into POD's earned-value engine, and the retainage and amount-due math is tracked per line, so a billing picture that used to live in a stack of forms becomes queryable project data.
Construction billing methods guideFrequently asked questions
The form is only the surface
Behind every pay app is the schedule of values that drives it and the retainage that holds part of it back. Start with the document that defines the lines.