Back online
Construction Glossary · Change Management

Compensable vsNon-Compensable

Two delays can both be excusable and land completely differently on the ledger. One earns time. The other earns time and a check.

Definition

Compensable delay is an excusable, owner-caused delay for which the contractor is entitled to both a time extension and recovery of the added cost. Non-compensable delay is an excusable delay from a neutral event, such as force majeure or unusual weather, for which the contractor receives a time extension but no money. Both are excusable; only one comes with a check.

Same slip, two different ledgers

Both delays below are excusable, so both earn a time extension. Only the owner-caused one carries money with it.

Non-compensable (unusual weather)

20-day slip
+20 days
time extension only — no cost recovery

Compensable (late owner-furnished equipment)

20-day slip
+20 days
+ cost recovery
time and money

What a compensable claim actually recovers

Compensation is the proven added cost of being on site longer, tied to the delay window — not a round number chosen after the fact.

Extended general conditions

Superintendent, trailer, temporary utilities — the time-related overhead that keeps running

Idle / underused equipment

Machines held on site through the delay window

Escalation

Higher labor and material prices on work pushed into a later period

Unabsorbed home-office overhead

Where allowed, via a method such as the Eichleay formula

What decides it: who caused the delay
Delay causeWho bears itCompensable?
Late owner-furnished equipmentOwnerYes — time and money
Defective or late designOwnerYes — time and money
Differing site conditionOwner (allocated risk)Yes — time and money
Unusually severe weatherNeither partyNo — time only
Force majeureNeither partyNo — time only
Contractor under-manningContractorNeither — and LDs may apply

The weather-and-force-majeure case is covered in force majeure, and the owner's side of the ledger in liquidated damages.

How POD builds the cost record

POD's commercial intelligence captures the delay event, its cause, and the contemporaneous evidence a compensable claim rests on, then lines it up against the change-order pipeline it may convert into. The daily reports, the dated schedule context, and the cost records that prove extended general conditions and idle equipment all live in one place rather than scattered across inboxes. POD does not adjudicate whether a delay is compensable; it keeps the record that argues it, so the claim is documented as the job runs, not reconstructed under deadline.

Delay analysis methodologies guide

Frequently asked questions

The money follows responsibility

A blameless delay still may not be paid. Compensation needs an owner-caused event and the cost records to prove it.

Last updated: October 2026