Compensable vsNon-Compensable
Two delays can both be excusable and land completely differently on the ledger. One earns time. The other earns time and a check.
Compensable delay is an excusable, owner-caused delay for which the contractor is entitled to both a time extension and recovery of the added cost. Non-compensable delay is an excusable delay from a neutral event, such as force majeure or unusual weather, for which the contractor receives a time extension but no money. Both are excusable; only one comes with a check.
Same slip, two different ledgers
Both delays below are excusable, so both earn a time extension. Only the owner-caused one carries money with it.
Non-compensable (unusual weather)
Compensable (late owner-furnished equipment)
What a compensable claim actually recovers
Compensation is the proven added cost of being on site longer, tied to the delay window — not a round number chosen after the fact.
Extended general conditions
Superintendent, trailer, temporary utilities — the time-related overhead that keeps running
Idle / underused equipment
Machines held on site through the delay window
Escalation
Higher labor and material prices on work pushed into a later period
Unabsorbed home-office overhead
Where allowed, via a method such as the Eichleay formula
| Delay cause | Who bears it | Compensable? |
|---|---|---|
| Late owner-furnished equipment | Owner | Yes — time and money |
| Defective or late design | Owner | Yes — time and money |
| Differing site condition | Owner (allocated risk) | Yes — time and money |
| Unusually severe weather | Neither party | No — time only |
| Force majeure | Neither party | No — time only |
| Contractor under-manning | Contractor | Neither — and LDs may apply |
The weather-and-force-majeure case is covered in force majeure, and the owner's side of the ledger in liquidated damages.
How POD builds the cost record
POD's commercial intelligence captures the delay event, its cause, and the contemporaneous evidence a compensable claim rests on, then lines it up against the change-order pipeline it may convert into. The daily reports, the dated schedule context, and the cost records that prove extended general conditions and idle equipment all live in one place rather than scattered across inboxes. POD does not adjudicate whether a delay is compensable; it keeps the record that argues it, so the claim is documented as the job runs, not reconstructed under deadline.
Delay analysis methodologies guideFrequently asked questions
The money follows responsibility
A blameless delay still may not be paid. Compensation needs an owner-caused event and the cost records to prove it.