ConstructionSubmittals
Before a material is fabricated, the contractor proves it matches the drawings. That proof is a submittal, and the review cycle behind it can make or break a lead time.
A submittal is a document, shop drawing, product sample, or data sheet the contractor provides to the design team for review and approval before materials are fabricated or installed. It confirms that what the contractor intends to furnish matches the contract documents, and it is tracked and aged on a submittal log.
The review cycle
The subcontractor prepares it, the general contractor reviews and forwards it, and the design team returns it with an action. If it comes back "revise and resubmit," the loop starts over, and each loop costs time.
What gets submitted, and how it comes back
| Review action | What it means |
|---|---|
| Approved | Proceed as submitted |
| Approved as noted | Proceed, incorporate the marked corrections, no resubmit needed |
| Revise and resubmit | Fix the issues and send it back for another review |
| Rejected | Does not meet the requirements; a new submittal is needed |
Submittals include shop drawings, product data, material samples, and quality certificates. A shop drawing is one type of submittal, not a separate document.
A submittal delay is a schedule delay
A large project can carry several hundred submittals. A single long-lead item, switchgear or custom curtain wall, may need its submittal approved months before installation. A submittal sitting in review is a schedule risk hiding in a stack of paperwork, which is why the log is aged against the dates the field actually needs each material.
How POD tracks submittals
POD keeps a submittal register alongside its other project logs, so each submittal's status and age are tracked in one place rather than scattered across email threads and spreadsheets. With the open items and their ages visible together, a submittal sitting in review surfaces as the schedule risk it is, instead of staying buried in paperwork.
RFI & submittal management guideFrequently asked questions
The paperwork that gates the work
Submittals, RFIs, and change orders are the records that keep a project coordinated. Each one is a question the field needs answered.