The last mile of a project. The building works and the owner can move in, but a list of small fixes stands between substantial completion and the final check.
A punch list is the list of minor incomplete or deficient items that remain after a construction project reaches substantial completion, none of which materially impairs the owner's use of the work. Each item is assigned, corrected, and verified, and the project reaches final completion only once the whole list is closed out.
From substantial to final completion
Say the walkthrough produces 80 items. Each is assigned, corrected, and verified. The project reaches final completion only when the last one is closed.
Two milestones, one list between them
Substantial completion
The owner can occupy and use the work. Warranties start, risk and insurance shift to the owner, liquidated damages stop, and most retainage is released. The punch list is born here.
Final completion
Every punch item is corrected and verified, the closeout documents are delivered, the lien waivers are in, and the last of the retainage is released. The job is done.
How POD tracks the punch list
POD keeps a punch-list register alongside its other project logs, so open and closed items are tracked in one place rather than on a clipboard that lives in one person's truck. With the remaining count and the oldest open items visible together, the gap between substantial and final completion is a measured distance instead of a vague "almost done."
Punch list management guideFrequently asked questions
The punch list is tied to the money
The last retainage does not release until the list is closed. That is the owner's leverage, and the contractor's incentive to finish.