Over- & Under-Billing
The gap between what you have billed and what you have actually earned. A small, early overbilling funds the job; a large one can sink a company that still looks profitable.
Over- and under-billing is the gap between what a contractor has billed to date and the revenue it has actually earned to date. Overbilling means billings run ahead of earned revenue (a balance-sheet liability); underbilling means earned revenue runs ahead of billings (an asset). The difference is tracked on the WIP schedule.
Billed is not earned
On our project, $5.7M has been billed, including $0.3M of stored materials not yet installed. But earned revenue, at 45% of the $12.0M contract, is $5.4M. The job is overbilled by $0.3M.
$5.7M − $5.4M = +$0.3M (overbilled)
Two directions, two meanings
Overbilled
Billed ahead of earned revenue. Shows on the balance sheet as a liability (billings in excess of costs and earnings).
A little funds the job. A lot becomes job borrowing: paying today's costs with tomorrow's unearned billings.
Underbilled
Earned revenue ahead of billings. Shows as an asset (costs in excess of billings).
Often just slow billing, but it means the contractor is financing the owner's work, tying up cash it has already earned.
How POD surfaces the billing position
POD reads the amount billed to date from your pay applications and keeps the percent complete beside it, so the inputs a work-in-progress schedule needs stay current instead of going stale between quarterly closes. Striking the over- or under-billed position is still the accountant's call on the WIP schedule, but the numbers that feed it are kept up to date as each application lands.
Construction WIP schedule guideFrequently asked questions
The billing picture, start to finish
From the schedule of values to the pay application to the billing position, these terms are one chain. Walk it from the beginning.