Back online
Construction Glossary · Billing & Pay Apps

Retainagein Construction

A slice of every payment the owner keeps until the job is done. It is the leverage that gets the punch list finished, and a real cash-flow cost to the contractor until it is released.

Definition

Retainage (also called retention) is the portion of each construction progress payment, usually five to ten percent, that the owner withholds until the work is substantially or fully complete. It accrues in a running balance across every pay application and is released near the end of the job, protecting the owner and motivating the contractor to finish cleanly.

It accrues, then it releases

On our $12.0M project at 10%, each pay application adds to the retained balance. By Application 8, with $5.7M completed and stored, $0.57M is being held, all of it released once the job is finished and closed out.

$0.57M heldApp 1App 8Releasedat completion

Who it protects, and what it costs

Protects the owner

The held balance is a reserve against defects, incomplete work, and liens. As long as the owner holds a meaningful slice, the contractor has reason to come back and finish right.

Costs the contractor

Retained dollars are earned but unpaid, so the contractor finances them until release. On a long job the cash-flow cost is real, which is why contractors negotiate the rate and press for reduction.

Flows down to subs

A general contractor usually withholds the same retainage from its subcontractors. So the owner holds from the GC, and the GC holds from the trades, all the way down the chain.

How POD tracks retainage

When POD reads a pay application, it separates the retainage from the amount due and reconciles the running retained balance across applications, so the held total and the net check each period are explicit rather than buried in the form. That means the retained balance and the amount still due are tracked figures, ready for the closeout conversation instead of recomputed by hand at the end.

Construction retainage guide

Frequently asked questions

Retainage is one line of the math

It sits between what was earned and what gets paid. See the full line-item arithmetic that turns completed work into a check.

Last updated: October 2026