Percentage ofCompletion
A long job earns its revenue a month at a time, not all at the end. The percentage-of-completion method is how the books keep pace with the build.
The percentage-of-completion (POC) method is the accounting method that recognizes a construction contract's revenue and profit gradually as the work is performed, not all at once at the end. Under the cost-based approach, percent complete equals costs incurred to date divided by total estimated cost, and recognized revenue equals percent complete times the contract value. It is the standard revenue-recognition method for long-term construction contracts, and it is distinct from EVM percent complete, which measures physical progress for project control.
The cost-to-cost calculation
Costs incurred over total estimated cost gives percent complete; times the contract value gives revenue earned to date. On our project, 50 percent complete earns $6.0M of the $12.0M contract.
Two accounting methods, one control measure
Percentage-of-completion and completed-contract are revenue-recognition choices. EVM percent complete is a different thing entirely, for the project team, not the books.
| Recognizes revenue | Answers | Audience | |
|---|---|---|---|
| Percentage-of-completion | Gradually, as work is done | How much revenue is earned | Accounting / financials |
| Completed-contract | All at the end | How much revenue is earned | Accounting (short jobs) |
| EVM percent complete | Not a revenue measure | How much work is physically done | The project team |
The control-side measure is EVM percent complete; earned revenue vs billed is the WIP schedule.
How POD relates to percentage-of-completion
POD already holds the inputs a cost-based percentage-of-completion calculation needs: the cost to date from your pay applications, the budgeted cost of the work, and the contract value with approved change orders, each individually authoritative and reconciled. POD runs the cost-based calculation as a reporting layer over the project's confirmed, sealed of-record: the Earned Revenue view in Project Controls shows cost-based percent complete and the total earned revenue it produces. The denominator is the confirmed construction budget, labeled as such, never the CPI-derived EAC, so the result stays independent of the earned-value forecast instead of restating it. If actual cost is confirmed on only part of the job, or nothing has been sealed yet, the figure is withheld with a prompt rather than shown as a partial number. POD is not your accounting system of record, and what gets booked as recognized revenue and profit is still your accountant's decision. The calculation gives them a reconciled figure and the inputs behind it to check against.
Percentage-of-completion guideFrequently asked questions
Earned revenue meets billed revenue
Once you know revenue earned, the next question is how it compares to what you have billed. That gap, over or under, is the WIP schedule.