Back online
Construction Glossary · Financial & Accounting

The WIPSchedule

One row per job, from contract to billing position. It is the report that tells a contractor, a surety, and a bank what the backlog is really worth.

Definition

A work-in-progress (WIP) schedule is the construction financial report, usually run monthly, that reconciles for each active project the contract value, estimated cost, cost incurred to date, percent complete, revenue earned, and amount billed, and shows whether each job is overbilled or underbilled. It is the core management report a construction CFO, surety, and lender rely on to see the true financial position of the backlog, project by project.

Earned versus billed is the whole point

At 50 percent complete our $12.0M job has earned $6.0M but billed only $5.0M, so it is underbilled $1.0M, cash tied up in work not yet invoiced. The reverse, billed above earned, would be overbilled.

Revenue earned (50% × $12.0M)$6.0MBilled to date$5.0Munderbilled $1.0M

One project, walked across the row

Every WIP column follows from the one before it. Contract and cost give percent complete; percent complete gives earned revenue; earned minus billed gives the over/under position.

ColumnOur projectFrom
Contract value$12.0MContract + approved COs
Estimated total cost$10.8MBudget / forecast
Cost to date$5.4MPay applications
Percent complete50%Cost ÷ est. cost
Revenue earned$6.0M% × contract
Billed to date$5.0MPay applications
PositionUnderbilled $1.0MBilled − earned

The last row is over/under billing; the earned-revenue step is revenue recognition.

How POD relates to the WIP schedule

Every input a WIP schedule needs already lives in POD and is individually authoritative: the contract value with approved change orders, the cost to date and amounts billed from your pay applications, and the budgeted cost of the work. Rolling those into the earned-revenue and over/under-billed figures of a full WIP schedule is POD's documented revenue-recognition methodology, a defined layer that sits beside the live EVM engine. POD does not compute the WIP schedule’s earned-revenue or over/under-billed outputs as live figures today, and it is not your accounting system of record. What it offers is one reconciled source for the inputs the schedule is built from.

Construction WIP schedule guide

Frequently asked questions

The WIP is one of three lenses

Earned value tracks performance, the budget tracks cost, and the WIP schedule tracks revenue against billing. Each answers a different question about the same job.

Last updated: October 2026