Schedule Variance &SPI
The schedule half of earned value, and the one with a catch: it reads the lag in dollars, not days, and it quietly heals itself at the finish line.
The schedule performance index (SPI) is earned value divided by planned value; it measures how much of the planned pace the work is actually keeping. Schedule variance (SV) is earned value minus planned value, the same reading in dollars. An SPI below 1.0, or a negative SV, means the project is behind schedule.
Earned pace vs planned pace
Both readings compare the work done against the work the plan called for by now. On our $12.0M project, the plan said $6.0M would be earned by month 8, but only $5.4M is.
SPI = EV ÷ PV = $5.4M ÷ $6.0M = 0.90
Schedule variance gives the lag in money; SPI gives it as a pace you can compare across projects. Both say the same thing here: the work is running behind plan.
The two catches to know
It reads in dollars, not days. A schedule variance of −$0.6M tells you how much planned work is outstanding, not how many days late you are. Turning that into weeks takes a different method.
It heals itself at the end. Because all planned value is eventually earned, SPI returns to exactly 1.0 at completion even on a project that finished late. Near the finish, the index stops telling the truth.
Both problems are why earned schedule exists: it measures the lag along the time axis, so a late job reads late right up to the last day.
How POD reads schedule performance
POD derives SPI and schedule variance from the earned value and the baseline planned value it already holds, and pairs them with its schedule reading so the dollar lag and the critical-path picture sit side by side. It reads float and the critical path from imported P6 and MS Project files rather than recomputing them, so the schedule story stays anchored to the contractor's own program.
Earned schedule & SPI guideFrequently asked questions
Cost and schedule, read together
SPI pairs with the cost index to place a project in the earned-value quadrant, then both feed the forecast to completion.