What Is Earned ValueManagement?
One method that measures cost and schedule at the same time, from three numbers you already track. Here is what it is, the two questions it answers, and a worked example you can follow line by line.
Earned value management (EVM) is a project-controls method that measures cost and schedule performance from three numbers: planned value, earned value, and actual cost. Comparing them tells you, in dollars, whether a project is ahead or behind schedule and over or under budget.
The three numbers EVM runs on
Everything in earned value comes from these three figures, read at the same moment in time (the data date). Get them honest and the rest is arithmetic.
What you planned to have spent by the data date (month 8 of a $12M job, 50% planned).
The budgeted worth of the work actually finished so far (45% complete).
What you have actually spent to get that work done.
Each of these is defined in full in planned value, earned value & actual cost.
The two questions it answers
EVM turns the three numbers into two readings. One is about money, one is about time, and each comes as both a dollar variance and a ratio you can compare project to project.
Are we over or under budget?
Compare the worth of work done against what it cost. Cost variance is EV minus AC; the cost performance index is EV divided by AC. Below 1.0 means each dollar is buying less than a dollar of progress.
Cost variance & CPIAre we ahead or behind schedule?
Compare the worth of work done against what should have been done. Schedule variance is EV minus PV; the schedule performance index is EV divided by PV. Below 1.0 means the work is lagging the plan.
Schedule variance & SPIA worked example, line by line
Take a $12.0M project at month 8. The plan said 50% of the budget would be earned by now. Only 45% is done, and $6.3M has been spent. Four subtractions and ratios turn that into a verdict.
- Planned Value (PV)
- $6.0M50% of $12.0M planned by month 8
- Earned Value (EV)
- $5.4M45% actually complete × $12.0M
- Actual Cost (AC)
- $6.3Mcost booked to date
- Cost Variance (CV = EV − AC)
- −$0.9Mover budget
- Schedule Variance (SV = EV − PV)
- −$0.6Mbehind schedule
- CPI (EV ÷ AC)
- 0.86$0.86 earned per $1 spent
- SPI (EV ÷ PV)
- 0.9090% of planned pace
Extend the trend and the forecast finish is about $14.0M (BAC ÷ CPI), a projected $2.0M overrun. See the S-curve for how that reads over time.
The one chart EVM draws: our example project lands in the lower-left, behind schedule and over budget.
Why not just compare budget to actual?
The usual two-number comparison is blind to how much work the money actually bought. Earned value adds the missing third number.
| Question | Budget vs actual | Earned value |
|---|---|---|
| Numbers used | Budget, actual spend | Planned value, earned value, actual cost |
| Our example reads | $6.0M planned, $6.3M spent, so "slightly over" | $5.4M earned, so behind and over, by a known amount |
| Schedule insight | None | SV / SPI tell you the pace |
| Forecast | Guesswork | EAC from CPI: about $14.0M |
Where earned value goes wrong
Treating money spent as progress earned
Spending roughly half the budget does not mean half the work is done. Earned value is the budgeted worth of completed work, not the cash that left the account. Confusing the two is the single most common EVM error and it always flatters the numbers.
Measuring percent complete by feel
If percent complete is a month-end gut estimate, earned value is fiction and so is every index built on it. Agree an objective rule for each work type before the work starts: units installed, milestones hit, or a weighted-step method.
Running it without a frozen baseline
Planned value only means something against a baseline that does not move. If the plan is quietly re-cut every month to match reality, the schedule variance is always near zero and the method tells you nothing.
How POD handles earned value
POD computes earned value rather than asking you to key it in. It holds the budget as an immutable baseline, reads progress from the pay applications and confirmations you already produce, and derives CV, SV, CPI, and SPI from the three source numbers each period. Because the baseline is versioned, the schedule variance stays honest even after an approved change, and the S-curve is drawn from the same figures the indices use.
Frequently asked questions
See it on a live project
POD turns the pay apps and progress you already report into a computed earned-value picture, baseline and forecast included, without a controls analyst keying numbers.