Time & MaterialsTicket

The price gets negotiated later. The ticket is what proves, day by day, what the extra work actually took.

Definition

A time-and-materials (T&M) ticket is the daily record of labor hours, equipment, and materials used on work billed on a time-and-materials basis, typically extra or changed work not yet priced. Signed in the field each day, it is the evidence behind a T&M change-order claim.

What makes up the ticket

A T&M ticket is simple on its face, three line items added together, but each one carries its own proof burden. Labor needs names or trade counts and hours; equipment needs the piece and the hours or day rate; materials need the quantity and the unit cost. A ticket missing one of the three is incomplete evidence for the claim it is meant to support.

Labor8.5 hrs+Equipment1 excavator+Materialsrebar, formsDaily T&M Ticket TotalSigned daily, backup for the T&M claim

Three line items, one dispute risk each

Every category on the ticket gets challenged a different way when the backup is thin.

Line itemWhat it capturesDispute risk if missing
LaborWorker or trade, hours worked, sometimes the rateHours get challenged without a daily headcount
EquipmentPiece of equipment, hours or day rate, idle vs. workingIdle time is often disputed as not billable
MaterialsQuantity and unit cost tied to the specific scopeMaterials without a quantity back-up are cut first

A signed ticket is only as strong as the record it sits inside, see the daily construction report and the field report for how that surrounding record is built.

How POD handles T&M tickets

POD reads the daily reports and photos that document time-and-materials work, so the labor, equipment, and materials behind a T&M claim live with the dated record. POD does not generate or price your T&M tickets.

Construction daily report guide

Frequently asked questions

The ticket is the proof, not the price

Totaling a stack of signed tickets is what turns the work into a number. Pricing that number against contract rates is a separate step.