SubstantialCompletion
Not finished. Usable. One date that starts warranties, stops liquidated damages, and moves most of the retainage.
Substantial completion is the milestone when the work is complete enough for the owner to occupy or use it for its intended purpose, even with minor punch items left outstanding. It typically starts warranties, shifts risk and insurance, ends liquidated damages, and triggers release of most retainage.
The milestone that moves everything else
Substantial completion sits between start and final completion, not at the end. What is left after it is a shrinking punch list, not an unfinished building.
What the date actually triggers
Four things move on this single date, which is why it is negotiated so carefully.
| Trigger | Before SC | After SC |
|---|---|---|
| Warranty clock | Not running | Starts running on most systems |
| Liquidated damages | Accruing if behind schedule | Stop accruing |
| Retainage | Fully held | Most released, a smaller amount held to final |
The items left open become the punch list that has to close before final completion and the last of the retainage.
How POD handles substantial completion
POD reads the punch list and the dated field record that substantial completion turns on, so the state of the work is visible against the milestone. POD does not certify substantial completion; the architect or owner does.
Punch list management guideFrequently asked questions
Usable is the milestone, closed is the finish
What remains after substantial completion is the punch list standing between this date and the last retainage check.