UnbilledAccruals
The rebar is on site and the crew worked through the thirtieth, but the invoices will not show up until the middle of next month. An accrual puts that cost in the month it belongs to.
Unbilled accruals are estimated liabilities a contractor books at period end for work performed or materials delivered on site that no vendor or subcontractor has invoiced yet: month-end subcontractor labor, time-and-materials crews, equipment rental days, and stock already on the ground. They are added to paid and payable amounts so that the incurred cost of the period is not understated, and they reverse when the real invoice arrives.
The invoices lag the work. The accrual closes the gap.
In this month the project took delivery of $1.1M of work and material, but only $0.7M of it has been invoiced by the time the books close. Booking a $0.4M accrual for the rest means the cost report describes the month that actually happened, not the slice of it the vendors got around to billing.
What gets accrued, and from what evidence
An accrual is only as good as the field record behind it. The usual month-end candidates, and the document that prices each one.
| Accrual | Typical trigger | Priced from |
|---|---|---|
| Subcontractor labor | Lump-sum work done since the last pay request | Percent complete on the sub schedule of values |
| Time-and-materials crews | Hours worked through month end | Daily reports and timesheets at contract rates |
| Equipment rental | Machines on site past the last rental invoice | Rental agreement daily or weekly rate |
| Delivered materials | Stock received, not yet billed by the supplier | Delivery tickets at purchase-order price |
Once invoiced, each line moves out of accruals and into accounts payable; together with what has been paid they make up incurred cost.
The field record that prices the accrual
The accrual itself is an accounting entry, and POD does not book it or carry a separate accrual ledger. What POD holds is the evidence an accrual is built from: the daily reports with hours by crew, the deliveries logged on site, and the equipment on the job each day, kept as structured records rather than loose paperwork. At month end the question is no longer which crews worked the last week or what arrived on the twenty-eighth; the record already says so. The actual cost you then confirm, accruals included, is what POD sets against physical progress to read cost performance.
How accruals feed the money flowFrequently asked questions
Cost the month that happened
Accruals complete the incurred-cost picture. From there the money runs through percent complete, earned revenue, and billing. The guide follows one job all the way around.