IncurredCost

The bank statement says $3.2M. The work has already consumed $4.5M. Incurred cost is the number that counts what the job has used, not what the accounts department has gotten around to paying.

Definition

Incurred cost, also called actual cost or ACWP, is the economic value of the work a project has consumed to date, counted regardless of when the cash moves. It is the sum of three parts: invoices already paid, approved invoices still sitting in accounts payable, and unbilled accruals for work or materials received but not yet invoiced. It leaves out open commitments on purchase orders that have not been worked and change orders that have not been approved.

Three layers add up to one actual cost

Against an $8.5M cost budget, $3.2M has been paid out, $0.9M of approved invoices is waiting in accounts payable, and $0.4M of delivered work has no invoice yet. Stack the three and the job has incurred $4.5M. Count only the first layer and you are $1.3M short of the truth.

Cost budget (BAC) $8.5Mnot yet incurredPaid $3.2MAP $0.9MAccruals $0.4MIncurred $4.5M
Paid + AP + Accruals = Incurred
$3.2M + $0.9M + $0.4M = $4.5M

What goes in, and what stays out

Each layer carries a different kind of evidence. Paid has a cleared check. Accounts payable has an approved invoice. An accrual has a delivery ticket or a timesheet and an estimate. Open purchase orders and pending changes have none of these yet, so they wait outside.

ComponentWhat it isCash moved?Counted?
PaidVendor and sub invoices already settledYesYes
Accounts payableApproved invoices logged but not yet paidNot yetYes
Unbilled accrualsWork or materials received, no invoice yetNoYes, as an estimate
Open commitmentsSigned POs for work not yet performedNoNo
Pending change ordersScope not yet approved by the ownerNoNo

The open commitments belong to committed cost; the whole circuit from incurred cost to earned revenue to billing is walked in the construction finance money-flow guide.

How POD uses actual cost

POD takes the actual cost figure from the pay applications and cost records you confirm, keeps it apart from open commitments, and sets it against earned value drawn from real physical progress, so the cost performance index, the estimate at completion, and the variance at completion are computed from the actual cost you confirm. The paid, payable, and accrued split is your accounting system's job: POD does not divide the ledger into those three layers for you. What it does is make sure the actual cost you bring in is compared to progress that was measured in the field, not inferred from spending.

Follow the money from cost to cash

Frequently asked questions

Actual cost is only the first link

Incurred cost feeds percent complete, which feeds earned revenue, which is set against what you billed. One guide walks the whole chain with a single worked example.