Back online
← Construction Project Controls

Constructionretainage

Retainage is your money, held until the end.

A slice of every payment you earn is held back until the job is done. That is retainage, and it is not a fee. It is your money, parked in the owner's account, and on a thin-margin job it can add up to most of your profit. The trick is knowing exactly how much is held, how much you can bill for now, and how much is already back.

Your money
Held
Why it matters

Revenue you earned that the owner keeps until you finish. Not a fee, a holdback.

Bill it now
Releasable
Why it matters

Retention that has met a release trigger and is just sitting there, unbilled.

Profit, parked
The drag
Why it matters

On a thin-margin job, most of your profit can be trapped in retainage until closeout.

What retainage is

Retainage, also called retention, is a percentage of each progress payment that the owner withholds until the work is substantially or fully complete. It is security that the job gets finished and closed out. Commonly it is 5 to 10 percent, set by the contract and sometimes by law on public work.

The key thing controls-side is what it is not. It is not a fee and not a deduction from what you earned. It is money you have already earned, held back and paid later, so it belongs on the books as a receivable. Forget that and the job looks less valuable than it is, and the cash it represents quietly finances the owner instead of you.

How it is held and released

Retainage accrues a little at a time and comes back in stages. The exact triggers are set by the contract, but the shape is consistent, and none of the releases happen on their own.

StageWhat happens to the retainage
Each pay applicationThe owner withholds the retainage percentage, commonly 5 to 10 percent, from the amount earned that period.
Half completeWhere the contract allows, the rate may drop, releasing part of the retainage already accrued.
Substantial completionThe bulk of the balance is released, less a holdback kept against the remaining punch list.
Final acceptanceThe last retainage is released once the punch list is closed and the work is formally accepted.

A worked example

A $50M contract carries 10 percent retainage. With $30M of work in place, the owner has withheld $3.0M in retainage so far. Of that, $0.6M has already been released, $0.9M has met a release trigger and is billable right now, and $1.5M is still held against work not yet complete. If the job's margin is about $4M, that $3.0M of retainage is roughly three quarters of the profit, sitting in someone else's account. The $0.9M is the piece to notice: it is releasable today, and it only comes back if someone bills for it.

The retention stack

The whole column is the $3.0M held back, ten percent skimmed off every pay application and stacked up. Green at the bottom is what has been released. The glowing amber band is releasable now, billable today. The slate on top is still held until the work behind it is done.

$3.0M retained$1.5M still held$0.9M releasable now$0.6M released10% of each pay-app

Getting it back is a discipline

Retainage does not release itself. When a trigger is met, a rate reduction at half completion or a phase reaching substantial completion, the money becomes billable, but it stays in the owner's account until someone raises the invoice for it. The releasable balance is the easiest cash on the job to leave behind, precisely because nothing forces the issue.

And it flows both ways. A general contractor holds retention from its subcontractors while the owner holds it from the general contractor. Managing only one side hides the real position: the cash you are owed on top, and the cash you owe below, move on different triggers and different dates. The discipline is to carry held, releasable, and released for both, and to bill for release the moment a trigger is met.

The retention position, reconciled

The same $3.0M, split into what is retained, what is eligible for release, and what has already come back, with the release schedule that says when the rest is due. It turns a single line at the bottom of a pay application into a position you can actually manage.

Retainage Reconciler

POD
10% retainage

Retainage composition

0%Released
$0
Total Retainage
Released$0
Eligible$0
Held$0

Release schedule

Phase 1 acceptedThis period
$0
Substantial completionAt closeout
$0

Balances

$0
Released
$0
Pending Release
+$0
Variance
Retainage on track. $600K released of $3.0M total.

Four ways it goes wrong

Treating retainage as a fee, not a receivable

Retainage is money you earned and will get back, not a cost of doing the work. Booking it as gone, or forgetting it, understates what the job is actually worth to you.

Leaving releasable retention unbilled

Retention that has met its release trigger does not come back on its own. If nobody bills for it, it sits in the owner’s account earning you nothing while you finance the job.

Missing the reduction trigger

Many contracts cut the retainage rate at half completion. Miss the trigger and you leave cash in the holdback that the contract already says you are allowed to take.

Ignoring the sub side

A general contractor holds retention from its subcontractors while the owner holds it from the GC. Track only one side and the real two-way cash position goes blurry.

Tallied at closeout vs current every period

Retainage only helps your cash while there is a trigger left to bill against. The difference between a number you reconcile at the end and a position you can act on is whether held, releasable, and released are kept apart as the pay applications come in.

Tallied at closeout
  • ·Retainage is a single column added up at the end of the job
  • ·Held, releasable, and released are lumped into one figure
  • ·Release triggers are tracked by memory, not by the system
  • ·The releasable balance sitting unbilled is invisible until final
Read and kept current
  • ·POD reads the pay applications your job already produces
  • ·Retained, releasable, and released stay separated per project
  • ·The balance eligible for release surfaces every period
  • ·The cash tied up in retainage is visible, not discovered at the end

POD reads the pay applications your job produces and keeps the retention position current per project, so the cash tied up in retainage is visible every period. It pairs with the WIP schedule, billing methods, and the schedule of values the retainage is withheld against.

Retainage questions

What is retainage in construction?

Retainage, also called retention, is a percentage of each progress payment that the owner withholds until the work is substantially or fully complete. It is a form of security that the contractor will finish and close out the job. It is not a fee or a deduction from what you earned; it is money you have earned that is held back and paid later, so it belongs on the books as a receivable, not a cost.

What is a typical retainage percentage in construction?

Retainage is commonly 5 to 10 percent of each payment, set by the contract and sometimes by state law on public work. Many contracts start at 10 percent and reduce to 5 percent at a defined milestone, often half completion. The exact figure and the reduction terms vary widely, which is why the number on your contract, and the trigger that changes it, both matter more than any rule of thumb.

What is the difference between retainage and retention?

They are the same thing: money withheld from progress payments until completion. Retainage is the term more common in the United States and retention the term more common in the United Kingdom and Commonwealth countries. Some contracts and accounting systems use one word for the amount withheld and the other for the running balance, but there is no substantive difference in what the money is.

When is retainage released?

Retainage is typically released in stages: sometimes a partial release when a milestone such as half completion is reached, the bulk at substantial completion less a holdback for the punch list, and the final amount once the punch list is closed and the work is accepted. The exact triggers are set by the contract. Retention that has met a trigger is not released automatically; the contractor usually has to bill for it.

Can retainage be reduced during a project?

Often, yes. Many contracts provide for the retainage rate to drop, for example from 10 percent to 5 percent, once the job reaches a defined point such as half completion or a satisfactory performance record. Some jurisdictions require it. The reduction only helps if someone tracks the trigger and bills for the release, because it does not happen on its own.

How does POD help track retainage?

POD reads the pay applications your job already produces and keeps the retention position current per project, separating what has been retained, what has been released, and what is eligible for release under the schedule, so the cash tied up in retainage is visible every period rather than reconciled at closeout. Because the same platform holds billing, budget, and forecast, the retained balance is read from the same numbers as the rest of the job.

See the cash you can bill for now

POD keeps the retention position current

Begin with the free budget tracker, then let POD read the pay applications already moving through your jobs, so held, releasable, and released retention stay separated every period.