ConstructionDraw

One payment, released as the work goes in. Stack the draws and you have the project’s cash coming in.

Definition

A construction draw is a single payment released against a project as work is completed. Each draw equals the work completed that period plus stored materials, less retainage and everything already paid, which is the net amount due on the pay application. The draw schedule is the planned sequence of these payments across the job, the owner’s or lender’s plan for releasing funds against progress.

Each period’s release, stacked

Every bar adds that period’s draw to the running total. Eight periods in, $5.13M has been drawn; this period’s draw, the bright cap, is $0.63M.

12345678$0.63MCumulative drawn $5.13Mpay-app period

How one draw is calculated

The draw is the net amount due on the pay application, built cumulatively so any earlier error corrects itself.

Work completed to date$5.40M
+ Stored materials$0.30M
= Total completed & stored$5.70M
− Retainage (10%)−$0.57M
= Earned less retainage$5.13M
− Prior draws−$4.50M
= This draw (net due)$0.63M

That net-due figure is covered in full under work completed & net amount due; the withheld slice is retainage.

How POD reads the draw

POD reads each pay application into its net-amount-due figure, the draw for that period, from the work completed, stored materials, retainage, and prior certificates on the application, and keeps the running total alongside the budget and the cash position. So the draw you are claiming now sits in the same picture as what has already been drawn and what the job has cost. POD computes and surfaces the figure from the pay app you give it; it does not disburse the money, approve the draw, or run a lender’s draw schedule, which stay with the owner, the lender, and their inspectors.

Construction billing methods guide

Frequently asked questions

The draws are the cash curve

Stack every draw and you have money coming in. Set it against cost going out and you have the project’s cash flow.