Estimate atCompletion
Where earned value stops describing the past and starts forecasting the finish. EAC projects the final cost, ETC the work still left, and VAC the overrun you are heading for.
Estimate at completion (EAC) is the forecast of what a project will finally cost, projected from performance so far. Estimate to complete (ETC) is the cost of the work still remaining (EAC minus actual cost), and variance at completion (VAC) is the forecast overrun or underrun against budget (BAC minus EAC).
The forecast is the actual curve, extended
Our project has spent $6.3M by month 8 and is running at a CPI of 0.857. Project that efficiency forward and the finish lands near $14.0M, two million above the $12.0M budget.
EAC, ETC, and VAC
Estimate at Completion
The forecast total cost of the whole project. BAC ÷ CPI = $12.0M ÷ 0.857 = $14.0M.
Estimate to Complete
The cost of the work still left. EAC − AC = $14.0M − $6.3M = $7.7M.
Variance at Completion
The forecast overrun or underrun. BAC − EAC = $12.0M − $14.0M = −$2.0M.
The four EAC formulas
There is no single EAC. Which formula is right depends on what you believe about the work that remains.
| Formula | Use it when | Our example |
|---|---|---|
| EAC = BAC ÷ CPI | Current cost efficiency will continue (the safe default past ~20% complete) | $12.0M ÷ 0.857 = $14.0M |
| EAC = AC + (BAC − EV) | The overrun was a one-off; remaining work runs at budget | $6.3M + $6.6M = $12.9M |
| EAC = AC + (BAC − EV) ÷ (CPI × SPI) | Over budget and behind schedule, schedule pressure drives cost | $6.3M + $6.6M ÷ 0.771 = $14.9M |
| EAC = AC + bottom-up ETC | None of the above fit; re-estimate the remaining work | depends on the re-estimate |
How POD forecasts the finish
POD derives EAC, ETC, and VAC from the CPI it computes against the frozen baseline, updated each period as costs and progress land, so the forecast moves with the job rather than sitting stale in a spreadsheet. Because the baseline is versioned, an approved change resets what BAC and the forecast are measured against without losing the original.
The full EAC guideFrequently asked questions
From today's numbers to the finish
The forecast is only as honest as the index behind it. Pair EAC with the reality check of TCPI to see whether the budget is still reachable.