Back online
Construction Glossary · Earned Value

Estimate atCompletion

Where earned value stops describing the past and starts forecasting the finish. EAC projects the final cost, ETC the work still left, and VAC the overrun you are heading for.

Definition

Estimate at completion (EAC) is the forecast of what a project will finally cost, projected from performance so far. Estimate to complete (ETC) is the cost of the work still remaining (EAC minus actual cost), and variance at completion (VAC) is the forecast overrun or underrun against budget (BAC minus EAC).

The forecast is the actual curve, extended

Our project has spent $6.3M by month 8 and is running at a CPI of 0.857. Project that efficiency forward and the finish lands near $14.0M, two million above the $12.0M budget.

$0M$8M$16MMo 0Mo 8Mo 16BAC $12.0MData dateEAC $14.0MAC $6.3METC $7.7M (work left)VAC −$2.0M (forecast over)

EAC, ETC, and VAC

EAC

Estimate at Completion

The forecast total cost of the whole project. BAC ÷ CPI = $12.0M ÷ 0.857 = $14.0M.

ETC

Estimate to Complete

The cost of the work still left. EAC − AC = $14.0M − $6.3M = $7.7M.

VAC

Variance at Completion

The forecast overrun or underrun. BAC − EAC = $12.0M − $14.0M = −$2.0M.

The four EAC formulas

There is no single EAC. Which formula is right depends on what you believe about the work that remains.

FormulaUse it whenOur example
EAC = BAC ÷ CPICurrent cost efficiency will continue (the safe default past ~20% complete)$12.0M ÷ 0.857 = $14.0M
EAC = AC + (BAC − EV)The overrun was a one-off; remaining work runs at budget$6.3M + $6.6M = $12.9M
EAC = AC + (BAC − EV) ÷ (CPI × SPI)Over budget and behind schedule, schedule pressure drives cost$6.3M + $6.6M ÷ 0.771 = $14.9M
EAC = AC + bottom-up ETCNone of the above fit; re-estimate the remaining workdepends on the re-estimate

How POD forecasts the finish

POD derives EAC, ETC, and VAC from the CPI it computes against the frozen baseline, updated each period as costs and progress land, so the forecast moves with the job rather than sitting stale in a spreadsheet. Because the baseline is versioned, an approved change resets what BAC and the forecast are measured against without losing the original.

The full EAC guide

Frequently asked questions

From today's numbers to the finish

The forecast is only as honest as the index behind it. Pair EAC with the reality check of TCPI to see whether the budget is still reachable.

Last updated: October 2026