Back online
Construction Glossary · Earned Value

To-CompletePerformanceIndex

The reality check on every other index. TCPI is the efficiency the remaining work must hit to still land on budget, and comparing it to how the job has actually run tells you whether the target is real.

Definition

The to-complete performance index (TCPI) is the cost efficiency a project must achieve on all its remaining work to hit a target, usually the budget at completion. It is the budgeted work remaining divided by the money remaining: (BAC - EV) / (BAC - AC). Comparing it to the current CPI is a reality check on whether the budget is still reachable.

Can the budget still be hit?

Our project has $6.6M of budgeted work left ($12.0M − $5.4M) and $5.7M of budget left to spend ($12.0M − $6.3M). To finish within budget, every remaining dollar has to buy $1.16 of work.

TCPI = (BAC − EV) ÷ (BAC − AC)
= $6.6M ÷ $5.7M = 1.16

The job has run at 0.86. Asking it to suddenly run at 1.16 is not a plan, it is a hope. That gap is the signal to stop managing to the budget and start managing to the forecast.

1.0 = on budgetCPI 0.86how it has runTCPI 1.16what it now needsThe jump from 0.86 to 1.16 is the reality check

Two targets, two formulas

To hit the budget (BAC)

(BAC − EV) ÷ (BAC − AC)
= $6.6M ÷ $5.7M = 1.16

Use while the original budget is still the live target. Far above current CPI means the target is slipping out of reach.

To hit the forecast (EAC)

(BAC − EV) ÷ (EAC − AC)
= $6.6M ÷ $7.7M = 0.86

Use once the budget is superseded by a revised forecast. Landing back at the current CPI confirms the EAC is honest.

How POD frames the reality check

POD computes the current CPI and the budgeted-work-remaining from the same earned-value figures it already derives, so the required-to-complete efficiency sits next to the achieved efficiency rather than in a separate workbook. Seeing the two together is what turns a cheerful budget into an honest conversation about the forecast.

The full EVM guide

Frequently asked questions

The honest number to manage against

When TCPI outruns CPI, the budget is a story and the forecast is the truth. Both rest on a baseline that does not move.

Last updated: October 2026