GeneralConditions

The cost of simply having the job open: the super, the trailer, the power, the safety. It buys no permanent work, and it runs on a clock.

Definition

General conditions are the indirect, time-related costs of running a project that are not tied to any specific scope of permanent work: the superintendent and project-management staff, the site office and trailer, temporary utilities, shared equipment, safety, and cleanup. They sit on a distinct budget line, often roughly 8 to 15 percent of cost, and because many of them accrue for every day the job is open, they are the costs most exposed to a schedule delay.

What the time-cost is made of

Supervision dominates, but every slice accrues while the job is open. On our project that is roughly $90K a month, so two months of delay is about $180K of extended general conditions.

~$90K / month, every month the job runsSupervision & PM staffField office & trailerTemporary utilitiesShared equipmentSafety & cleanup

Project cost, not company cost

General conditions belong to this jobsite. Overhead belongs to the business. In a delay claim, they are proven in completely different ways.

General conditionsHome-office overheadProfit
ScopeThis jobsiteThe whole businessThe fee earned
Charged asA project budget lineA percentage markupA percentage markup
Proven in a delay byJobsite cost recordsA formula (e.g. Eichleay)Often not recoverable

Extended general conditions are the heart of a compensable delay claim, defended by the dated record.

How POD tracks general conditions

POD recognizes a general-conditions line in your confirmed budget as a level-of-effort item and tracks its budget and confirmed actual-to-date beside the schedule that drives it, so the time-related overhead is visible where the field record lives. Because general conditions accrue with time, seeing them beside a slipping finish date is where the value is: the dated daily record that would support an extended-general-conditions claim lives in the same place. POD reads and reconciles the general-conditions budget and actuals you provide; it does not compute a delay’s general-conditions damages or build your claim. It keeps the line and the record honest and together.

Construction cost management guide

Frequently asked questions

Time is the cost driver

General conditions turn a schedule slip straight into money. Which is why the finish date, and what it costs to hold it, is the whole game.