LNTP &Mobilization
Some work cannot wait for the ink to dry. A limited notice starts the long-lead items, and the money to mobilize is advanced, then recovered so billing never outruns the build.
A Limited Notice to Proceed (LNTP) authorizes a contractor to begin a defined, limited scope, such as long-lead procurement or mobilization, before the full contract is executed. Mobilization, or a down payment, is the up-front money to get started: moving in, the trailer, bonds, initial procurement. Because both are paid ahead of installed work, the advance is typically recovered across progress billings or folded into retention so it never outruns work in place.
Advanced, then recovered
On our $12.0M project, $600K is advanced at LNTP to mobilize and order long-lead items, then clawed back across the early progress billings until cumulative payment is tied to work in place.
A limited start, not a blank check
An LNTP is bounded by scope and dollars. It buys schedule on the items that cannot wait, without committing the owner to the whole contract early.
| Limited NTP (LNTP) | Full Notice to Proceed | |
|---|---|---|
| Authorizes | A defined early slice (long-lead, mobilization) | The entire contract scope |
| Owner commitment | Capped at a stated dollar limit | The full contract sum |
| When | Before the full contract is executed | On contract execution |
| Why | Protect the schedule on items that cannot wait | Begin the balance of the work |
How POD reads the advance
When POD reads a pay application, it recognizes an up-front mobilization, down-payment, or limited-notice line and folds it into its retention tracking, so the early advance is reflected against work in place rather than counted as ordinary earned value. That keeps cumulative billing honest on the periods where an advance would otherwise make progress look further along than it is. POD does not issue your LNTP or set the recovery schedule your contract specifies; it reads the pay-app the way the contract intends, so the advance and its recovery are both visible in the numbers.
Construction billing methods guideFrequently asked questions
The advance lives on the pay app
Mobilization is billed, recovered, and often offset by retainage, all on the same pay application that carries the rest of the work.