Back online
Construction Glossary · Financial & Accounting

Current ContractValue

The total every other number on the job is measured against, and it moves. The original sum, plus what has actually been signed. Nothing that is still a maybe.

Definition

The current (adjusted) contract value is the original contract sum plus every executed change order: the moving contract total that the schedule of values, pay-application percent complete, and earned revenue are all measured against. Only executed changes move it. Pending change orders, potential change orders, and change directives sit outside it as exposure until they are signed.

A ceiling that rises one signature at a time

The contract value is a staircase, not a curve. It holds flat for months, then steps up on the day a change order is executed, and holds flat again. On our project the original $11.4M took two steps to reach $12.0M. The third step, drawn dashed, is priced and sitting in the owner's inbox. Until it is signed, it is not part of the value.

Original contract sum $11.4MCO-01 +$0.25MCO-02 +$0.35MCurrent contract value $12.0MPCO-07+$0.4Mnot countedif executed: $12.4MSigningCO-01executedCO-02executedPCO-07pendingCurrent value $12.0M · $0.4M pending, not counted

Each executed change raises the whole ceiling to its right, which is why the value is a running total and not a list of adjustments. The pending change is real exposure, reported beside the value, never inside it.

One addition, and what it feeds

The equation is a sum, written below as the column a project accountant would actually run. Every variable links to its own definition. The last row is why the figure matters: it is the contract total that earned revenue is recognized against.

Equation
Our project, at the data date
Original contract sum, the signed price and the SOV total
$11.40M
+ CO-01, executed (differing site condition)
$0.25M
+ CO-02, executed (owner-added scope)
$0.35M
= Current contract value
$12.00M
PCO-07, pending: priced, unsigned, outside the value
$0.40M
What it drives
Earned Revenue = Cost POC% × Current Contract Value
50% × $12.0M = $6.0M

Executed is in. Everything else is exposure.

The whole discipline of the current contract value is a single test applied to every change on the job: has the owner signed it? The change order page covers the instrument; the PCO and directive page covers the pipeline before it. This is where each one lands.

Inside the value

Signed, so it counts

  • The original contract sum

    The price on the face of the agreement, which the first schedule of values breaks into lines.

  • Executed additive change orders

    Signed by the parties the contract names. Each one lifts the value on the day of signature.

  • Executed deductive change orders

    Signed scope cuts and credits lower the value by the same mechanism. The sum is a net.

  • Allowance reconciliations, once executed

    The difference between an allowance and the actual selection, after it is written up as a change order.

Outside it, in exposure

Real, but not yet agreed

  • Potential change orders

    Priced and submitted, not approved. They are the exposure band that sits above the current value.

  • Change directives

    The work may already be under way, but until the directive is converted to a change order the price is unsettled.

  • Claims and disputed back charges

    A demand is not an agreement. A claim enters the value only if it resolves into an executed change order.

  • Subcontract change orders

    They change the contractor's cost, not the owner's contract. Only client change orders move the value.

  • Contingency and reserve

    Budget, not contract. Drawing contingency changes where cost is expected, not what the owner agreed to pay.

What is measured against it, and what is not

The current contract value is the revenue side's ceiling: the pay application, the schedule of values, and earned revenue all foot to it. The cost side has its own ceiling, the budget at completion, and the earned-value figures are measured against that instead.

FigureFormulaMeasured against the contract value?
Earned revenueCost POC% × current contract valueYes. It is the ceiling earned revenue climbs toward.
Contract sum to date (G702)Original sum + net executed change ordersYes. This line is the current contract value.
Pay-app percent complete (G703)Work completed ÷ scheduled value, per lineYes. The scheduled values sum to it.
Balance to finishContract sum to date − total earnedYes. The unbilled remainder of the value.
EVM percent complete and earned value% complete × budget at completionNo. Measured against the cost budget (BAC).
CPI and SPIEV ÷ AC, EV ÷ PVNo. Cost-side indices; the contract value never enters.

On our project the two ceilings are $12.0M and $10.8M. The gap between them is the margin, which is exactly why the revenue lens and the earned-value lens must never share a denominator.

Three ways the value goes wrong

None of them is an arithmetic error. Each is a boundary drawn in the wrong place, and each one propagates into earned revenue, the billing position, and the WIP schedule.

01

Counting the pipeline

Add the pending $0.4M and the value reads $12.4M. At 50% cost-complete, earned revenue is now $6.2M instead of $6.0M: $0.2M of revenue recognized on scope the owner has not agreed to pay for, and the underbilled position is overstated by the same amount. If the owner rejects the change, the revenue reverses.

02

Confusing the contract with the budget

The $12.0M current contract value is the revenue ceiling. The $10.8M budget at completion is the cost ceiling. Earned revenue climbs toward the first; EVM percent complete and earned value are capped by the second. The $1.2M between them is the margin, and measuring either figure against the wrong ceiling erases it.

03

Letting the schedule of values drift

Every executed change order needs a new or adjusted line on the schedule of values so the G703 still sums to the current contract value. Skip it and the pay application carries a contract sum to date that disagrees with the signed contract, and every line's percent complete is measured against a total that no longer exists.

How POD maintains the current contract value

POD carries one current contract value per project: the original client contract plus the executed client change orders, read from the same client change-order-of-record that the earned-value baseline is built from, so the contract total and the plan everything is measured against move together rather than drifting apart on separate tabs. That figure is the contract total the live Earned Revenue view in Project Controls measures against: cost percent complete times the current contract value gives total earned revenue, and billed-to-date, taken gross from the client pay applications, against that gives the over- or under-billed position. Three rules keep it honest. Only executed client change orders move it; a potential change order or a directive stays in the change-order log as visible exposure until it is signed. Subcontract change orders never raise it, because they change the contractor's cost, not the owner's contract. And if the change-order record cannot be read, the earned-revenue figures are withheld with a prompt rather than computed against the original sum as though nothing had changed. POD is not your accounting system of record: the value it carries is the reconciled operating figure with every executed change behind it, and the transaction price on the books remains the accountant's call.

Frequently asked questions

The ceiling is set. Now climb it.

Multiply the current contract value by cost percent complete and you have the revenue the job has actually earned, whether or not a single invoice has gone out.

Last updated: November 2026