EarnedRevenue
The revenue you have earned by building, whether or not you have billed for it yet. One number, easily confused with two others that sit right beside it on every job.
Earned revenue is the share of a construction contract a contractor has earned by performing the work, recognized as cost percent complete times the current contract value, whether or not it has been billed yet. It is the revenue-recognition lens on a job, distinct from EVM earned value, which measures performance, and from billings, which measure cash position.
One job. Three numbers that look alike.
Taken at the same data date on the same $12.0M project, these three figures sit within a few hundred thousand dollars of each other and mean entirely different things. Mistake one for another and the WIP schedule, the cost performance index, or the cash forecast is wrong.
Earned Revenue
What the contractor has earned, at contract price. 50% cost-complete on the $12.0M current contract value. Carries the margin.
Earned Value (EV)
The budgeted cost of the work actually done. About 49% of the $10.8M budget at completion. No margin, never above budget.
Billed to Date
What has been invoiced on the pay applications, including $0.3M of stored material. Runs ahead of or behind the earned figure.
The equation, and the two it rests on
Earned revenue is a single multiplication, but each factor is itself a defined term with its own page. Every variable below links to its definition; the current contract value is the original sum plus executed change orders only.
The EAC-circularity trap
The denominator of cost POC% must be a bottom-up estimate: actual cost plus a genuine re-estimate of the cost to complete. On our job the accountant holds that estimate at $10.8M, so POC is 50%. The EVM side, extrapolating from a CPI of 0.97, forecasts EAC = BAC ÷ CPI = $11.1M. The two are allowed to differ. That difference is the independence the whole check depends on.
Feed the CPI-derived EAC into the POC formula instead and the algebra collapses: AC ÷ (BAC ÷ CPI) = (AC × CPI) ÷ BAC = EV ÷ BAC, which is EVM percent complete. On our numbers, $5.4M ÷ $11.1M and $5.25M ÷ $10.8M are both 48.6%. The accounting lens has become a restatement of the performance lens, and the over- or under-billed position stops telling you anything CPI did not already say.
Earned and billed are two curves, not two bars
Over the life of the job, earned revenue climbs an S-curve toward the current contract value while billings follow their own path: ahead early on mobilization and front-loaded lines, behind later as invoicing lags the work. The shaded gap between them is the billing position at every data date, not just today's.
At month 8 the earned curve reads $6.0M and the billed curve $5.7M: underbilled by $0.3M, a contract asset. Four months earlier the same job was overbilled. Neither point is the story; the shape of the gap is.
Where each number lives
Different question, different formula, different ceiling, different reader. The only thing the three share is a project.
| Answers | Formula | Ceiling | Who reads it | |
|---|---|---|---|---|
| Earned Revenue | How much revenue have we earned? | Cost POC% × Current Contract Value | Contract value ($12.0M) | Controller, CFO, surety, lender |
| Earned Value (EV) | How much of the budgeted work is done? | % Complete × BAC | Budget at completion ($10.8M) | Project manager, controls team |
| Billed to Date | How much have we invoiced? | Sum of pay applications, gross | Contract value, via the SOV | PM, accounts receivable, the owner |
Billed minus earned is the over/under-billed position. EV against actual cost is CPI. Earned revenue against the contract is the income statement.
How POD reports earned revenue
POD reports earned revenue as a reporting layer over the project's confirmed, sealed of-record, the same record its earned-value views read, so the three lenses on this page come from one set of numbers rather than three spreadsheets. The Earned Revenue view in Project Controls shows cost-based percent complete, total earned revenue, and the over- or under-billed position, with the current contract value built from the original sum plus executed client change orders and billed-to-date taken gross from the client pay applications. Two honesty rules shape it. The cost basis is the confirmed construction budget, labeled as such, never the CPI-derived EAC, so the figure stays independent of the performance lens and clear of the circularity above. And when actual cost is confirmed on only some of the construction lines, or no of-record has been sealed, the figures are withheld with a prompt rather than shown as a lower bound or a fabricated zero. POD is not your accounting system of record: recognizing revenue and profit on the books remains the accountant's call. What POD gives the controller is the reconciled position and every input behind it.
Percentage-of-completion guideFrequently asked questions
Earned is one side of the ledger
Set earned revenue against what has actually been billed and the gap between them, over or under, becomes a balance-sheet position with a name.